Pontchartrain Park

6025 Providence Place is in Pontchartrain Park, zoned S-RS (Newer neighborhoods, single-family homes). The city has 8 permits on record here; the most recent, an electrical vacancy permit, was filed in November 2013. 8 are still open. A demolition permit was filed in November 2008. There were 2 past code enforcement cases, the latest in November 2011, all closed. On this block in the past year: 24 requests to 311 and 3 calls to police.

Zoning
S-RS
Historic district
None
Council district
D
Ward
9
Lot size
5,037 sq ft
Parcel
41086366

Everything on record here

10 records, newest first · 8 open

  1. Permit Electrical Vacancy Permit Issued

    VACANCY

    Permit
    13-44183-EVAC
    Type
    Electrical Vacancy
    Work
    Electrical Vacancy
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Patrick Mel Thomas
    Days from application to issue
    0
    Expires
    May 13, 2014

    See this permit on One Stop

  2. Permit Electrical Repair / Replacement / Addition Permit Issued

    Work Descripton: VACANCY Historical Import Type: Permits Electrical Residential Repair-Replacement-Addition User: DMFOLEY Tracking: 86147608551 Status: Permit Issuance Active Status Date: 1/4/2012 12:00:00 AM Owner: Baptiste Cheryl J Owner Address: Etal C/O Maudrey Richardson 3652 Lancaster Street, New Orleans, LA 70131 Owner Edited By: 1/4/2012 by DMFOLEY

    Permit
    12ELC-00148
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Malone Electrical
    Days from application to issue
    0
    Expires
    Jul 4, 2012
  3. Code enforcement Case CEHB-11-1710 Closed

    The property was inspected on 02/13/2013 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 13-44183-EVAC.

  4. Code enforcement Case HCES-11-03133 Closed

    The case was filed on 04/26/2011 but has since been closed without further action.

    1. Inspection: Inspection Violation Unoccupied

    The city links this case to permit 13-44183-EVAC.

  5. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    REWIRE- TAKE OVER JOB FROM ROY FARTHING WHO IS NO LONGER AFFILIATED WITH THIS ADDRESS AS PER OWNER EFFECTIVE 04/30/2009. SEE ATTACHED.

    Permit
    09ELC-07757
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Hart Electric
    Days from application to issue
    10
  6. Permit General Mechanical Application Acceptance - Approved

    INSTALL ELEC WAF AND 3-TON A\C. ROBERT GOODWIN (#3135)

    Permit
    09MCH-02294
    Type
    General Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $70
    Contractor
    Rob's A/C & Heating
    Days from application to issue
    5
  7. Permit Construction Loop Application Acceptance - Approved

    TEMP POLE

    Permit
    09ELC-01979
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Farthing Electric
    Days from application to issue
    10
  8. Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved

    NEW CONSTRUCTION

    Permit
    09ELC-01980
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $162
    Contractor
    Farthing Electric
    Days from application to issue
    10
  9. Permit New Construction Inspection - Completed No Requirements

    Construct a 1393 sq ft 1-story single-family house as per plans.

    Permit
    09BLD-00069
    Type
    New Construction
    Work
    New
    Estimated cost (applicant’s figure)
    $107,800
    Fees
    $698
    Contractor
    David Ranglack, Architect, LLC
    Days from application to issue
    8
  10. Permit Demolition Inspection - Completed No Requirements

    Demolition. All permits issued for demolition require the contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection. (Weigh tickets or invoice from an approved landfill will meet this requirement.) It is unlawful to leave debris, Section 103.20.2; City of New Orleans IBC Building Code)

    Permit
    08BLD-08072
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $7,800
    Fees
    $-100
    Days from application to issue
    5