Gentilly Terrace
5101 Elysian Fields Avenue is in Gentilly Terrace, zoned S-RS (Newer neighborhoods, single-family homes). The city has 7 permits on record here; the most recent, a mechanical HVAC permit, was filed in December 2021. 1 is still open. A demolition permit was filed in December 2006. There were 3 past code enforcement cases, the latest in December 2010, all closed. On this block in the past year: 7 requests to 311 and 3 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 8
- Lot size
- 6,001 sq ft
- Parcel
- 41087193
Everything on record here
10 records, newest first · 1 open
-
Permit Mechanical HVAC Permit Finaled
Final inspection,
- Permit
- 21-35029-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $65,000
- Fees
- $116
- Days from application to issue
- 12
- Expires
- Jun 28, 2022
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Cancelled
INSTALL 2 NEW A/C SYSTEMS A 4 TON AND A 3 TON WITH GAS AIR HANDLERS NEW DUCT WORK AND ALL RELATED MATERIALS
- Permit
- 21-02441-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $12,000
- Fees
- $103
- Days from application to issue
- 1
- Expires
- Jul 27, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Issued
Install new gas tines to water heaters and other appliances
- Permit
- 21-01684-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $0
- Fees
- $60
- Contractor
- Daniel Lewis Lambert, Jr
- Days from application to issue
- 1
- Expires
- Jul 21, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
New construction
- Permit
- 20-50065-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $2,500
- Fees
- $172
- Contractor
- Samuel Madison Tillman
- Days from application to issue
- 1
- Expires
- Jun 23, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Construction Loop Permit Cancelled
Construction loop
- Permit
- 20-50063-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $250
- Fees
- $40
- Contractor
- Samuel Madison Tillman
- Days from application to issue
- 1
- Expires
- Jun 23, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
New construction of a 2-stry, 2500 sq ft single family residence as per plans.
- Permit
- 20-45477-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $250,000
- Fees
- $1,560
- Contractor
- CBA Home Builders Inc
- Days from application to issue
- 44
- Expires
- Jun 18, 2021
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Code enforcement Case HCEVU-10-02151 Closed
A hearing was held on 01/21/2011 with a result of "Guilty Public Nuisance".
- Inspection: Inspection Violation Unoccupied
- Inspection: Inspection Violation Posted No WIP
- Hearing: Initial Hearing Guilty Public Nuisance
- Inspection: Inspection Violation WIP
The city links this case to permit 21-35029-HVAC.
-
Code enforcement Case HCES-10-01200 Closed
The case was filed on 12/01/2010 but has since been closed without further action.
The city links this case to permit 21-35029-HVAC.
-
Code enforcement Case ENVHADJ-2009105P Closed
The property was inspected on 10/28/2008 with a finding of "Complete". The file was subsequently closed.
- Inspection: Inspection Complete
The city links this case to permit 21-35029-HVAC.
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. slab remains.
- Permit
- 06BLD-11749
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Days from application to issue
- 4