Desire Area

2833 Metropolitan Street is in Desire Area, zoned S-RD (Newer neighborhoods, two-family homes and townhouses). The city has 5 permits on record here; the most recent, a general mechanical permit, was filed in April 2011. 5 are still open. A demolition permit was filed in February 2008. On this block in the past year: 0 requests to 311 and 1 call to police.

Zoning
S-RD
Historic district
None
Council district
D
Ward
9
Lot size
5,084 sq ft
Parcel
41090458

Everything on record here

5 records, newest first · 5 open

  1. Permit General Mechanical Inspection - Completed

    INSTALL ELEC WAF AND 3-TON A\C. LEROY McCOY (#6051)

    Permit
    11MCH-02748
    Type
    General Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $65
    Contractor
    Roy's Repair & Services
    Days from application to issue
    0
  2. Permit Electrical Service / Circuit / Feeder Permit Issuance - Active

    NEW CONSTRUCTION & LOW VOLTAGE- 11BLD-01641

    Permit
    11ELC-03641
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $145
    Contractor
    Lockett Construction Co.
    Days from application to issue
    0
  3. Permit Construction Loop Permit Issuance - Active

    TEMP POLE- 11BLD-01641

    Permit
    11ELC-03642
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Lockett Construction Co.
    Days from application to issue
    0
  4. Permit New Construction Inspection - Completed

    NEW COSNTRUCTION OF A 1-STRY 1250 SQ FT SINGLE FAMILY RESIDENCE AS PER PLANS.

    Permit
    11BLD-01641
    Type
    New Construction
    Work
    New
    Estimated cost (applicant’s figure)
    $110,000
    Fees
    $720
    Days from application to issue
    6
  5. Permit Demolition Inspection - Completed No Requirements

    DEMOLISH SINGLE-FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.

    Permit
    08BLD-00924
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $125
    Contractor
    DRC Emergency, DRC Emergency
    Days from application to issue
    8