4716 Pecan Street is in Plum Orchard, zoned S-RD (Newer neighborhoods, two-family homes and townhouses). The city has 5 permits on record here; the most recent, a mechanical permit, was filed in March 2008. 5 are still open. A demolition permit was filed in September 2006. On this block in the past year: 15 requests to 311 and 10 calls to police.

Zoning
S-RD
Historic district
None
Council district
E
Ward
9
Lot size
7,582 sq ft
Parcel
41091763

Everything on record here

5 records, newest first · 5 open

  1. Permit Mechanical Permit Issuance Active

    GAS LINE AND GAS WATER HEATER. STEVE CHAMBERS (#19676)

    Permit
    08MCH-05271
    Type
    Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $35
  2. Permit General Mechanical Application Acceptance - Approved

    GAS WAF AND 3-TON CONDENSER . DEAN WALTERS (#27869317 4 )

    Permit
    08MCH-01656
    Type
    General Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $67
    Contractor
    Complete Residential Service LLC
    Days from application to issue
    5
  3. Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved

    REWIRE

    Permit
    07ELC-23027
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $141
    Contractor
    Ben's Electrical Service
    Days from application to issue
    10
  4. Permit New Construction Certificate of Occupancy - Issued w/Meter

    NEW CONSTRUCTION OF A 1-STORY SINGLE FAMILY DWELLING AS PER SKETCH.

    Permit
    07BLD-02302
    Type
    New Construction
    Work
    New
    Estimated cost (applicant’s figure)
    $150,000
    Fees
    $800
    Days from application to issue
    9
  5. Permit Demolition Inspection - Completed No Requirements

    DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.

    Permit
    06BLD-08405
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $125
    Days from application to issue
    5