7431 Arbor Drive is in Little Woods, zoned S-RS (Newer neighborhoods, single-family homes). The city has 6 permits on record here; the most recent, a general mechanical permit, was filed in November 2008. 6 are still open. A demolition permit was filed in June 2006. On this block in the past year: 0 requests to 311 and 4 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- E
- Ward
- 9
- Lot size
- 14,740 sq ft
- Parcel
- 41094904
Everything on record here
6 records, newest first · 6 open
-
Permit General Mechanical Application Acceptance - Approved
INSTALL 2-GAS WAF AND METER . K. HELMSTETTER (#1687)
- Permit
- 08MCH-15956
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $70
- Contractor
- Kerry's A/C & Ref.
- Days from application to issue
- 5
-
Permit General Mechanical Application Acceptance - Approved
*ADAM DANIEL FURNACE A/C X 2 CK#3754
- Permit
- 08MCH-15668
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $74
- Contractor
- Arctic Air By Adan Daniel LLC
- Days from application to issue
- 5
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
NEW CONSTRUCTION- SENT TO BUILDING 10/31/2008. RELEASED TO ENTERGY 11/11/2008.
- Permit
- 08ELC-22567
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $162
- Contractor
- First Contact Electric
- Days from application to issue
- 10
-
Permit Construction Loop Application Acceptance - Approved
TEMP POLE
- Permit
- 08ELC-08201
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- First Contact Electric
- Days from application to issue
- 10
-
Permit New Construction Certificate of Occupancy - Issued w/Meter
NEW CONSTRUCTION OF A 2-STORY SINGLE FAMILY DWELLING AS PER PLANS.
- Permit
- 07BLD-11382
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $250,000
- Fees
- $1,550
- Days from application to issue
- 22
-
Permit Demolition Inspection - Completed No Requirements
DEMOLITION-PLAN TO REBUILD. CONTRACTOR MUST REMOVE ALL DEBRIS WITHIN 72 HOURS, AND GET PROOF OF PROPER DISPOSAL FOR FINAL INSPECTION. GENTILLY DISTRICT.
- Permit
- 06BLD-04013
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $3,000
- Fees
- $90
- Days from application to issue
- 5