Pines Village

168 Harbor Circle is in Pines Village, zoned HI (Heavy industrial: higher-impact manufacturing and storage). The city has 10 permits on record here; the most recent, an attached sign permit, was filed in February 2026. 4 are still open. On this block in the past year: 1 request to 311 and 8 calls to police.

Zoning
HI
Historic district
None
Council district
D
Ward
9
Lot size
20,940 sq ft
Parcel
41097782

Everything on record here

10 records, newest first · 4 open

  1. Permit Attached Sign Other

    Requesting permit RJS Towing llc

    Permit
    26-05532-SATT
    Type
    Attached Sign
    Work
    Attached Sign
    Estimated cost (applicant’s figure)
    $0
    Fees
    $230
    Days from application to issue
    6
    Expires
    Sep 3, 2026
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Other

    six month gas vacancy inspection

    Permit
    25-39879-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $600
    Fees
    $30
    Contractor
    Eric Anthony Brossette
    Days from application to issue
    12
    Expires
    Jul 12, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Electrical Service / Circuit / Feeder Other

    installing new 3 phase service of the one that was stolen off building Exceeding the scope of the permit or failure to obtain the proper building permits will result in additional fees as well as delays in issuance of a certificate of occupancy, meter release, and any other remedy allowed by law. Such remedies include but are not limited to revocation of all permits for the property.

    Permit
    25-32699-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $15,000
    Fees
    $103
    Contractor
    Salvadore J. Ditta
    Days from application to issue
    94
    Expires
    Jul 22, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Electrical Repair / Replacement / Addition Other

    replacing 200 amp 3 phase meter pan, main disconnect, and 40 circuit indoor panel. Install 6 high bay lights with 6 wall packs, Install LED trim replacements on existing recess cans. Replace existing outlets and switches with new ones

    Permit
    25-28176-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $15,000
    Fees
    $100
    Contractor
    SALVADORE J. DITTA
    1. Application submitted

    See this permit on One Stop

  5. Permit Renovation (Non-Structural) Other

    applying for a change of use permit for a towing and storage facility. painting and clean up-no construction

    Permit
    25-23330-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $0
    Fees
    $120
    Days from application to issue
    13
    Expires
    Feb 13, 2026
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  6. Permit Construction Loop Permit Finaled

    Request Temporary Power Const. Loop in order to provide lighting for interior demolition. An application for interior debris removal demolition is associated with this permit.

    Permit
    23-32379-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $40
    Contractor
    Kimberly J Poree, Sr.
    Days from application to issue
    23
    Expires
    Jun 20, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Interior Demolition Permit Issued

    Remove debris in interior of building. This is nonstructural debris. The demolition is to clean the building and prepare it for an Electrical Permit for Temporary Power. The building will remain as existing.

    Permit
    23-32377-DEMI
    Type
    Interior Demolition
    Work
    Interior Demolition
    Estimated cost (applicant’s figure)
    $2,700
    Fees
    $135
    Days from application to issue
    23
    Expires
    Jun 19, 2024
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  8. Permit General Mechanical Inspection - Completed

    METER OUT OVER SIX MONTHS. JOHN LOGIUDICE (#1008)

    Permit
    07MCH-03527
    Type
    General Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    Year Round Htg & A/C
    Days from application to issue
    5
  9. Permit Electrical Permit Issuance Active

    water damaged

    Permit
    06ELC-11719
    Type
    Electrical
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
  10. Permit Electrical

    GENERAL REPAIRS OFFICE BUILDING REPAIR DAMAGE TO SREVICE CAUSE BY ROTTEN POLE. POLE BROKE AND FELL

    Permit
    E01009322
    Type
    Electrical
    Days from application to issue
    0

    Placed here by a known alternate street name from “168 HARBOR CR”.