Read Blvd West

4743 Bundy Road is in Read Blvd West, zoned S-RS (Newer neighborhoods, single-family homes). The city has 8 permits on record here; the most recent, a mechanical fuel gas permit, was filed in December 2024. 1 is still open. A building here was demolished under the NORA program, completed in December 2011. On this block in the past year: 13 requests to 311 and 13 calls to police.

Zoning
S-RS
Historic district
None
Council district
E
Ward
9
Lot size
5,447 sq ft
Parcel
41098879

Everything on record here

9 records, newest first · 1 open

  1. Permit Mechanical Fuel Gas Permit Finaled

    New gas line. New water heater

    Permit
    24-36644-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $1,700
    Fees
    $40
    Contractor
    William Leroy Hoffman, Jr
    Days from application to issue
    1
    Expires
    Jun 6, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Driveway/ Curb Cut and Restoration Other

    Driveway

    Permit
    24-32134-RDRV
    Type
    Driveway/ Curb Cut and Restoration
    Work
    Driveway/ Curb Cut and Restoration
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Contractor
    Eddrin Williams
    Days from application to issue
    36
    Expires
    May 26, 2025

    See this permit on One Stop

  3. Permit Plumbing Permit Other

    Plumbing for new construction home

    Permit
    24-22970-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $120
    Contractor
    William Leroy Hoffman, Jr
    Days from application to issue
    1
    Expires
    Jan 26, 2025

    See this permit on One Stop

  4. Permit Mechanical HVAC Other

    Install Hvac System . Single zone 4 ton system. The rough-in phase involves placing ductwork, vents, and registers to facilitate air circulation and temperature control in each zone. The trim-out phase includes connecting the HVAC units, Installing trim, installing thermostats, and testing the system for proper operation and efficiency.

    Permit
    24-22571-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,400
    Fees
    $68
    Contractor
    Ali Hussein Bazzi
    Days from application to issue
    0
    Expires
    Jan 23, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Electrical Service / Circuit / Feeder Other

    Wire new house and temp pole

    Permit
    24-21918-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $18,000
    Fees
    $130
    Contractor
    Christopher Robert Hoke
    Days from application to issue
    20
    Expires
    Feb 7, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  6. Permit Construction Loop Permit Finaled

    temp pole

    Permit
    24-21920-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $300
    Fees
    $40
    Contractor
    Christopher Robert Hoke
    Days from application to issue
    5
    Expires
    Jan 23, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit New Construction Other

    New construction single floor and single family dwelling 4 bd 2 bath total sqft 1818

    Permit
    24-13700-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $238,000
    Fees
    $1,488
    Contractor
    WILLSTAND, INC
    Days from application to issue
    63
    Expires
    Jan 9, 2025
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  8. Demolition NORA demolition Completed
    Program
    NORA
    Units
    1
    Started
    Nov 10, 2011
    Completed
    Dec 22, 2011

    Source: data.nola.gov BlightStatus demolitions (2009–2019, no longer updated)

  9. Permit Residential Permit Issuance Active

    demolish single family house to grade. contractor shall remove and dispose of all debris within 72 hours of completion. proof of disposal required at time of final inspection. separate permit required from sewerage and water board to cap sewer lines and

    Permit
    11BLD-06804
    Type
    Residential
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $145