Filmore
5216 Paris Avenue is in Filmore, zoned S-RS (Newer neighborhoods, single-family homes). The city has 7 permits on record here; the most recent, a mechanical HVAC permit, was filed in September 2017. 1 is still open. A demolition permit was filed in August 2013. There is 1 open code enforcement case. On this block in the past year: 10 requests to 311 and 6 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 7,221 sq ft
- Parcel
- 41106164
Everything on record here
9 records, newest first · 2 open
-
Permit Mechanical HVAC Permit Finaled
install gas air handler and 5-ton a/c Anthony Beau (#11636) 17-00731-Newc
- Permit
- 17-30548-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $0
- Fees
- $76
- Contractor
- Anthony Beau
- Days from application to issue
- 0
- Expires
- Mar 6, 2018
-
Permit Mechanical Fuel Gas Permit Finaled
gas line/ wh/ david416-6533/ ck17148
- Permit
- 17-30013-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- David Carter Sr.
- Days from application to issue
- 0
- Expires
- Feb 28, 2018
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
17-00731 NewC
- Permit
- 17-27914-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $6,000
- Fees
- $157
- Contractor
- Melan Electric Inc
- Days from application to issue
- 0
- Expires
- Feb 14, 2018
-
Permit Construction Loop Permit Finaled
Permit #17-00731-NEWC
- Permit
- 17-17256-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $7,000
- Fees
- $40
- Contractor
- Melan Electric Inc
- Days from application to issue
- 2
- Expires
- Nov 18, 2017
-
Permit New Construction Permit Issued
Construct 2021 sq ft 1-story single-family dwelling as per plans.
- Permit
- 17-00731-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $185,000
- Fees
- $1,170
- Contractor
- Corne Construction LLC, Eugene Brian
- Days from application to issue
- 92
- Expires
- Oct 11, 2017
-
Code enforcement Case 16-08020-MPM Judgment
A hearing was held on 10/11/2016 with a result of "Guilty".
- Inspection
- Title Research
- Hearing
- Judgment
- In Compliance
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 159 Sidewalks
- Violation: 160 Weeds and Plant Growth
- Violation: 161 Rodent Harborage
- Inspection: Posting of Hearing Notice Violation: WIP
- Hearing: Initial Hearing Guilty
- Inspection: Posting of Judgment Violation: WIP
The city links this case to permit 17-30548-HVAC.
-
Code enforcement Case 16-07929-MPM Closed
The case was filed on 08/10/2016 but has since been closed without further action.
The city links this case to permit 17-30548-HVAC.
-
Permit Demolition Permit Finaled
Demolition to grade of a slab foundation. House was demolished under #07Bld-04558.
- Permit
- 13-34844-DEMO
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $160
- Contractor
- LL Bond & Company
- Days from application to issue
- 0
- Expires
- Feb 19, 2014
-
Permit Demolition Inspection - Completed No Requirements
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWAGE AND WATER BOARD TO CAP SWER LINES AND REMOVE WATER METERS. APPROVAL LETTER FROM LAW DEPT. ON FILE
- Permit
- 07BLD-04558
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Days from application to issue
- 5