5112 Cameron Boulevard is in St. Anthony, zoned S-RS (Newer neighborhoods, single-family homes). The city has 14 permits on record here; the most recent, a mechanical fuel gas permit, was filed in March 2023. 3 are still open. A demolition permit was filed in May 2007. On this block in the past year: 19 requests to 311 and 27 calls to police.

Zoning
S-RS
Historic district
None
Council district
D
Ward
7
Lot size
5,416 sq ft
Parcel
41107327

Everything on record here

14 records, newest first · 3 open

  1. Permit Mechanical Fuel Gas Permit Finaled

    Running approximately 90' of gas piping from gas meter to generator

    Permit
    23-08009-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $80
    Contractor
    Joey Buster Hickey
    Days from application to issue
    43
    Expires
    Nov 5, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Permit Cancelled

    Running 90' of gas piping from gas meter to generator.

    Permit
    23-07151-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $45
    Contractor
    Even Flow Plumbing Repair
    1. Application submitted

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Cancelled

    Installing approximately 90' of gas piping from meter to new generator

    Permit
    23-06680-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $0
    Contractor
    Even Flow Plumbing Repair
    1. Application submitted

    See this permit on One Stop

  4. Permit Permanent Generator Permit Finaled

    Installing a permanent generator for customer

    Permit
    23-05384-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $3,903
    Fees
    $100
    Contractor
    Roy Ellsworth Farthing Jr
    Days from application to issue
    7
    Expires
    Sep 6, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Accessory Structure Permit Issued

    Permeant generator installation

    Permit
    23-03644-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $3,903
    Fees
    $140
    Contractor
    Roy Ellsworth Farthing Jr
    Days from application to issue
    20
    Expires
    Aug 27, 2023
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  6. Permit Solar Permit Finaled

    Installation of 17 solar panels and electrical on existing residential structure.

    Permit
    19-33513-SOLR
    Type
    Solar
    Work
    Solar
    Estimated cost (applicant’s figure)
    $11,591
    Fees
    $49
    Contractor
    Amanda Hutchison
    Days from application to issue
    2
    Expires
    Apr 23, 2020

    See this permit on One Stop

  7. Permit Renovation (Non-Structural) Other

    Installation of 17 solar panels on an existing residential roof.

    Permit
    19-33379-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $11,591
    Fees
    $120
    Contractor
    Marc Jones Construction LLC
    Days from application to issue
    3
    Expires
    Apr 21, 2020
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Permit approved
    5. Issue date
    6. First inspection

    See this permit on One Stop

  8. Permit Mechanical Fuel Gas Permit Finaled

    6 month gas water heater electric

    Permit
    17-03916-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $3,500
    Fees
    $50
    Days from application to issue
    0
    Expires
    Aug 3, 2017

    See this permit on One Stop

  9. Permit Mechanical HVAC Permit Finaled

    4 ton ac

    Permit
    17-03915-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $73
    Days from application to issue
    4
    Expires
    Aug 7, 2017

    See this permit on One Stop

  10. Permit Construction Loop Permit Finaled

    TEMP POLE

    Permit
    16-40890-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $300
    Fees
    $40
    Days from application to issue
    14
    Expires
    Jun 28, 2017

    See this permit on One Stop

  11. Permit Electrical Service / Circuit / Feeder Permit Finaled

    200 amp 12 circuit rewire

    Permit
    16-35523-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $136
    Days from application to issue
    55
    Expires
    Jun 19, 2017

    See this permit on One Stop

  12. Permit New Construction Occupancy

    Construct a 1900 square foot dwelling as per plans.

    Permit
    16-31939-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $108,000
    Fees
    $708
    Contractor
    Damon's Air Cont & Heating LLC
    Days from application to issue
    15
    Expires
    Apr 11, 2017

    See this permit on One Stop

  13. Permit Demolition Inspection - Completed No Requirements

    HURRICANE DAMAGE REPAIRS TO INCLUDE: FLOORS, SHEETROCK, ROOF, PLUMBING, ELECTRICAL AND OTHER REPAIRS AS NEEDED TO MAKE THE HOME LIVEABLE

    Permit
    07BLD-05317
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $6,532
    Fees
    $110
    Contractor
    New Orleans Demolition Service, New Orleans Demolition Service
    Days from application to issue
    5
  14. Permit Demolition Application Acceptance - Approved No Review

    DEMOLISH DOUBLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. DOUBLE 5112-14 CAMERON BLVD

    Permit
    06BLD-10922
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $125
    Days from application to issue
    5