Dillard

1856 Carnot Street is in Dillard, zoned S-RS (Newer neighborhoods, single-family homes). The city has 5 permits on record here; the most recent, a mechanical permit, was filed in August 2011. 5 are still open. A demolition permit was filed in February 2009.

Zoning
S-RS
Historic district
None
Council district
D
Ward
7
Lot size
4,851 sq ft
Parcel
41107347

Everything on record here

5 records, newest first · 5 open

  1. Permit Mechanical Permit Issuance Active

    ajm311, ck 1171 john 756-8245 waf ac

    Permit
    11MCH-06557
    Type
    Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $65
  2. Permit Electrical Permit Issuance Active

    NEW CONSTRUCTION- 09BLD-02445

    Permit
    11ELC-08415
    Type
    Electrical
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $123
  3. Permit Electrical Service / Circuit / Feeder Permit Issuance - Active

    REWIRE- 09BLD-02445

    Permit
    10ELC-03221
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    Carr's Electric
    Days from application to issue
    0
  4. Permit New Construction Certificate of Occupancy - Issued w/Meter

    NEW CONSTRUCTION OF A 1-STORY SINGLE FAMILY DWELLING AS PER PLANS.

    Permit
    09BLD-02445
    Type
    New Construction
    Work
    New
    Estimated cost (applicant’s figure)
    $88,000
    Fees
    $578
    Days from application to issue
    13
  5. Permit Demolition Inspection - Completed

    DEMOLISH HURRICANE DAMAGED SINGLE TO GRADE AS PER OWNER’S REQUEST. A LICENSED PLUMBER MUST SECURE A SEPARATE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METERS PRIOR TO DEMOLITION. ANY FURTHER USE SHALL REQUIRE A SEPARATE PERMIT.

    Permit
    09BLD-00880
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Days from application to issue
    5