5225 Saint Bernard Avenue is in Filmore, zoned S-RS (Newer neighborhoods, single-family homes). The city has 7 permits on record here; the most recent, a mechanical fuel gas permit, was filed in July 2018. 2 are still open. A demolition permit was filed in August 2006. There was 1 past code enforcement case, the latest in March 2017, all closed. On this block in the past year: 2 requests to 311 and 3 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 10,876 sq ft
- Parcel
- 41108967
Everything on record here
8 records, newest first · 2 open
-
Permit Mechanical Fuel Gas Permit Finaled
New Line And Water Heater. 17-744842277
- Permit
- 18-24261-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $0
- Fees
- $35
- Contractor
- Brad Galpin
- Days from application to issue
- 0
- Expires
- Jan 23, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Rough - In .
- Permit
- 18-22775-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $160
- Contractor
- Bruce Michael Phillips
- Days from application to issue
- 0
- Expires
- Jan 10, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
5 Ton Gas HVAC system
- Permit
- 18-21646-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $7,475
- Fees
- $76
- Days from application to issue
- 0
- Expires
- Dec 28, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Construction Loop Permit Finaled
Temp Pole 18-09736-NEWC
- Permit
- 18-09736-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Bruce Michael Phillips
- Days from application to issue
- 0
- Expires
- Nov 18, 2018
- First inspection
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit New Construction Occupancy
Construct 2531 sq ft 1-story single-family dwelling with 793 sq ft attached garage as per plans.
- Permit
- 18-09736-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $340,000
- Fees
- $2,100
- Contractor
- Reve, Inc., L Dow Oliver & Associates
- Days from application to issue
- 47
- Expires
- Nov 8, 2018
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Code enforcement Case 17-02062-MPM Closed
A hearing was held on 06/06/2017 with a result of "Guilty: Abated".
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 160 Weeds and Plant Growth
- Inspection: Posting of Hearing Notice Violation: WIP
- Hearing: Initial Hearing Guilty: Abated
The city links this case to permit 18-24261-FGAS.
-
Permit Demolition Application Acceptance - Approved No Review
DEMOLISH TO GRADE AS PER OWNER'S REQUEST; HAUL AWAY DEBRIS WITHIN 72 HOURS OF DEMOLITION.
- Permit
- 06BLD-06319
- Type
- Demolition
- Estimated cost (applicant’s figure)
- $3,000
- Fees
- $0
Placed here by a known alternate street name from “5225 St Bernard”.
-
Permit Demolition Inspection - Completed No Requirements
DEMOLITION OF HURRICANE DAMAGED SINGLE FAMILY DWELLING TO GRADE; CONTRACTOR TO REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS AND TO HAVE A FINAL INSPECTION OF THE SITE; NEW CONSTRUCTION REQUIRES ANOTHER PERMIT
- Permit
- 06BLD-06357
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $90
- Days from application to issue
- 5