4600 New Orleans Street is in Dillard, zoned S-RS (Newer neighborhoods, single-family homes). The city has 5 permits on record here; the most recent, a mechanical fuel gas permit, was filed in November 2017. There were 3 past code enforcement cases, the latest in September 2014, all closed. On this block in the past year: 5 requests to 311 and 7 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 7,233 sq ft
- Parcel
- 41109334
Everything on record here
8 records, newest first
-
Permit Mechanical Fuel Gas Permit Finaled
Installation of a gas line and an electric water heater.
- Permit
- 17-39909-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $500
- Fees
- $35
- Contractor
- Neil Metoyer
- Days from application to issue
- 5
- Expires
- May 27, 2018
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Complete wire and low voltage.
- Permit
- 17-31073-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $3,500
- Fees
- $151
- Days from application to issue
- 1
- Expires
- Mar 13, 2018
-
Permit Mechanical HVAC Permit Finaled
Install 3.5 ton split, central heating and cooling system with 15KW electric heat.
- Permit
- 17-31061-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $8,000
- Fees
- $68
- Contractor
- Robert Phillips
- Days from application to issue
- 2
- Expires
- Mar 14, 2018
-
Permit Construction Loop Permit Finaled
Temp pole.
- Permit
- 17-29450-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $3,400
- Fees
- $40
- Days from application to issue
- 20
- Expires
- Mar 14, 2018
-
Permit New Construction Occupancy
Construct 1665 sq ft 2 story single-family residence as per plans. Catch basin must be converted into a drop inlet due to driveway encroachment.
- Permit
- 17-23774-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $158,000
- Fees
- $1,058
- Contractor
- Viewpoint Development & Construction, Elliot Hano
- Days from application to issue
- 28
- Expires
- Feb 8, 2018
-
Code enforcement Case 14-07986-MPM Closed
A hearing was held on 12/04/2014 with a result of "Guilty".
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 159 Sidewalks
- Violation: 160 Weeds and Plant Growth
- Inspection: Posting of Hearing Notice Violation: No WIP
- Hearing: Initial Hearing Guilty
- Inspection: Posting of Judgment Violation: WIP
The city links this case to permit 17-39909-FGAS.
-
Code enforcement Case 12-12370-PNBL Closed
A hearing was held on 10/03/2013 with a result of "Guilty: Public Nuisance Blight".
- Violation: 28-33 Duty to Mow Grass
- Violation: 28-20 Rodent Harborage
- Inspection: Inspection Violation: No WIP
- Inspection: Posting of Hearing Notice Violation: No WIP
- Hearing: Initial Hearing Guilty: Public Nuisance Blight
The city links this case to permit 17-39909-FGAS.
-
Code enforcement Case ENVHADJ-994079P Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 17-39909-FGAS.