Gentilly Terrace

2671 Acacia Street is in Gentilly Terrace, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). The city has 2 permits on record here; the most recent, a demolition permit, was filed in February 2012. 2 are still open. A demolition permit was filed in February 2012. A building here was demolished under the NORA program, completed in October 2012. On this block in the past year: 8 requests to 311 and 22 calls to police.

Zoning
HU-RD1
Historic district
None
National Register
Edgewood Park Historic District
Council district
D
Ward
8
Lot size
4,522 sq ft
Parcel
41110348

Everything on record here

3 records, newest first · 2 open

  1. Demolition NORA demolition Completed
    Program
    NORA
    Units
    1
    Started
    Jun 28, 2011
    Completed
    Oct 23, 2012

    Source: data.nola.gov BlightStatus demolitions (2009–2019, no longer updated)

  2. Permit Demolition Permit Issued

    Work Descripton: Demolish single family house to grade. Contractor shall remove and dispose of all debris within 72 hours of completion. Proof of disposal required at time of final inspection. Separate permit required from sewerage and water board to cap sewer lines and remove water meters. Historical Import Type: Permits Residential Single (One-Family Unit) Demolition User: EBALLARD Tracking: 86115684860 Status: Permit Issuance Active Status Date: 2/10/2012 12:00:00 AM Owner: Road Home Corporation Owner Address: 1201 N 3Rd St Ste 7-290, Baton Rouge, LA 70802 Owner Edited By: 2/10/2012 by EBALLARD

    Permit
    12BLD-00917
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $145
    Days from application to issue
    0
    Expires
    Aug 10, 2012

    See this permit on One Stop

  3. Permit Demolition Application Acceptance - Approved No Review

    DEMOLITION OF HURRICANE DAMAGED RESIDENCE

    Permit
    07BLD-00258
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $9,904
    Fees
    $-15
    Contractor
    New Orleans Demolition, New Orleans Demolition
    Days from application to issue
    5