10101 Lake Forest Boulevard is in Read Blvd East, zoned MU-1 (Medium-intensity mixed use, walkable centers with homes and shops). The city has 227 permits on record here; the most recent, a mechanical fuel gas permit, was filed in April 2022. 10 are still open. There were 8 past code enforcement cases, the latest in September 2017, all closed. On this block in the past year: 8 requests to 311 and 96 calls to police.

Zoning
MU-1
Historic district
None
Council district
E
Ward
9
Lot size
106,735 sq ft
Parcel
41114625

Everything on record here

208 records, newest first

Showing the latest 200 of 227 permits.

  1. Permit Mechanical Fuel Gas Permit Finaled

    New gas line for 8 tankless water heaters and 1 generator. These tankless water heaters are one hot water system for all 200 units in the building

    Permit
    22-11153-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $50,000
    Fees
    $284
    Days from application to issue
    6
    Expires
    Oct 19, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Moving Equipment Permit Finaled

    Installation Of Two ( 2 ) Geared, Traction Elevators

    Permit
    21-25940-MOVG
    Type
    Moving Equipment
    Work
    Moving Equipment
    Estimated cost (applicant’s figure)
    $0
    Fees
    $250
    Contractor
    H- Worth Elevator Co
    Days from application to issue
    0
    Expires
    Mar 16, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Street Cut Other

    Tying into existing sewerage manhole in the right of way

    Permit
    21-16097-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $315
    Days from application to issue
    25
    Expires
    Dec 29, 2021

    See this permit on One Stop

  4. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47614-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  5. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47615-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  6. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47616-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  7. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47617-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  8. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47618-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  9. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47619-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  10. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47620-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  11. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47621-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  12. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47622-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  13. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47623-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  14. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47624-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  15. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47625-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  16. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47626-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  17. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47627-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  18. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47628-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  19. Permit Electrical Service / Circuit / Feeder Permit Issued

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47629-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    Michael D Zemke
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  20. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47630-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  21. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47631-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  22. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47632-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  23. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47633-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  24. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47634-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  25. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47635-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  26. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47636-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  27. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47637-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  28. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47638-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  29. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47639-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  30. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47640-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 7, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  31. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47641-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  32. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47642-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  33. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47643-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  34. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47644-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  35. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47645-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  36. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47646-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  37. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47647-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  38. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47648-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  39. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47649-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  40. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47650-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  41. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47651-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 6, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  42. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47573-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  43. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47572-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  44. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47571-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  45. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47570-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  46. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47569-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  47. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47568-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  48. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47567-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  49. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47566-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  50. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47565-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  51. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47564-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  52. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47563-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  53. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47562-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  54. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47561-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  55. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47560-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  56. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47559-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Oct 5, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  57. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47558-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  58. Permit Electrical Service / Circuit / Feeder Permit Issued

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47557-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    Michael D Zemke
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  59. Permit Electrical Service / Circuit / Feeder Permit Issued

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47556-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    Michael D Zemke
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  60. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47555-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  61. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47554-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  62. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47553-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  63. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47552-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  64. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47551-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  65. Permit Electrical Service / Circuit / Feeder Permit Issued

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47550-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    Michael D Zemke
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  66. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47549-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  67. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47548-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  68. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47547-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  69. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47546-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  70. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47545-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  71. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47544-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  72. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47543-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  73. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47542-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  74. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47541-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  75. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47540-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  76. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47539-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  77. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47538-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  78. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47534-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 30, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  79. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47537-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 26, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  80. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47536-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 26, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  81. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47535-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 26, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  82. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47613-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  83. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47612-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  84. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47611-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  85. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47610-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  86. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47609-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  87. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47608-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  88. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47607-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  89. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47606-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  90. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47605-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  91. Permit Electrical Service / Circuit / Feeder Permit Issued

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47604-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    Michael D Zemke
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  92. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47603-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  93. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47602-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  94. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47601-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 24, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  95. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47600-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  96. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47599-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  97. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47598-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  98. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47597-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  99. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47596-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  100. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47595-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  101. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47594-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  102. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47593-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  103. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47592-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  104. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47591-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  105. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47590-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  106. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47589-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  107. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47588-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  108. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47587-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  109. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47586-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  110. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47585-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  111. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47584-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  112. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47583-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  113. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47582-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  114. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47581-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  115. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47580-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  116. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47579-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  117. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47578-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  118. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47577-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  119. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47576-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  120. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47575-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  121. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47533-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  122. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47532-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  123. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47531-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  124. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47530-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  125. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47528-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  126. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47458-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  127. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47457-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  128. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47456-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  129. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47455-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  130. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47454-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  131. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47453-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  132. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47452-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  133. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47451-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    1
    Expires
    Sep 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  134. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47450-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  135. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47449-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  136. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47448-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  137. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47447-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  138. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47446-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  139. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47445-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  140. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47444-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  141. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47652-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Sep 11, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  142. Permit Street Cut Other

    Upgrade system

    Permit
    21-06047-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $121
    Days from application to issue
    16
    Expires
    Sep 19, 2021

    See this permit on One Stop

  143. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47459-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  144. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47460-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  145. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47461-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  146. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47462-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  147. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47463-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  148. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47464-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  149. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47465-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  150. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47466-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  151. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47467-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  152. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47468-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  153. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47469-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  154. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47470-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  155. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47471-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  156. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47472-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  157. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47473-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  158. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47474-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  159. Permit Mechanical HVAC Permit Finaled

    Install (2) 2 ton gas split systems & (1) 20 ton split system WORK TO BE COMPELTED ON FIRST FLOOR COMMON AREA ONLY FOR HVAC (BLM) 20 ton unit is for common areas only

    Permit
    20-50179-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $942,500
    Fees
    $201
    Contractor
    Tktmj Inc
    Days from application to issue
    12
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  160. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47433-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jun 17, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  161. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47434-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jun 17, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  162. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47439-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    75
    Expires
    Sep 2, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  163. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47440-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    109
    Expires
    Oct 5, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  164. Permit Change of Address Permit Issued

    20-01898-RNVS multi family corrections to addresses REMOVE 10101 Lake Forest BLVD Apts 1505, 1506, 1507, 1508 ADD 10101 Lake Forest BLVD Apts 101, 102

    Permit
    20-49137-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Jun 11, 2021
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

    Placed here by the building address from “10101 Lake Forest Blvd Apt 101-Apt 1508”.

  165. Permit Electrical Service / Circuit / Feeder Permit Finaled

    RE-WIRE HOUSE METER 20-01898-RNVS

    Permit
    20-48156-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $1,615
    Contractor
    D Zemke D D Michael
    Days from application to issue
    0
    Expires
    Jun 1, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  166. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47653-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    108
    Expires
    Sep 11, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  167. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47574-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    120
    Expires
    Sep 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  168. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47443-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    112
    Expires
    Sep 15, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  169. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47441-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    36
    Expires
    Jun 29, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  170. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47475-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  171. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47476-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  172. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47477-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  173. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47478-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  174. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47479-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  175. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47480-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  176. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47481-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  177. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47482-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  178. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47483-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  179. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47484-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  180. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47485-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  181. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47486-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  182. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47487-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  183. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47488-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  184. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47489-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  185. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47490-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  186. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47504-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  187. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47503-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  188. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47502-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  189. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47501-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  190. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47500-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  191. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47499-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  192. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47498-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  193. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47497-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  194. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47496-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  195. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47495-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  196. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47494-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  197. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47493-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  198. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47492-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  199. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47491-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    42
    Expires
    Jul 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  200. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 100 AMP & 11 CIRCUITS 20-01898-RNVS

    Permit
    20-47505-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $103
    Contractor
    D Zemke D D Michael
    Days from application to issue
    36
    Expires
    Jun 29, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  201. Code enforcement Case 17-11581-MPM Closed

    The property was inspected on 09/14/2017 with a finding of "Violation: No WIP". The file was subsequently closed.

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 160 Weeds and Plant Growth
    4. Violation: 161 Rodent Harborage
    5. Violation: 163 Fences and Walls
    6. Violation: 165 Defacement of Property
    7. Violation: 167 Exterior Surfaces
    8. Violation: 167 Paint or Protective Treatment
    9. Violation: 167 Siding and Masonry
    10. Violation: 167 Metal Surfaces
    11. Violation: 168 Premises Identification
    12. Violation: 171 Exterior Walls
    13. Violation: 174 Decorative Features
    14. Violation: 179 Windows
    15. Violation: 179 Door Frames
    16. Violation: 182 Gates

    The city links this case to permit 22-11153-FGAS.

  202. Code enforcement Case 17-06271-MPM Closed

    The case was filed on 05/31/2017 but has since been closed without further action.

    The city links this case to permit 22-11153-FGAS.

  203. Code enforcement Case 14-08956-MPM Closed

    A hearing was held on 12/17/2014 with a result of "Guilty".

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 159 Driveways
    4. Violation: 159 Sidewalks
    5. Violation: 160 Weeds and Plant Growth
    6. Violation: 161 Rodent Harborage
    7. Violation: 163 Fences and Walls
    8. Violation: 165 Defacement of Property
    9. Violation: 167 Exterior Surfaces
    10. Violation: 167 Paint or Protective Treatment
    11. Violation: 167 Siding and Masonry
    12. Violation: 167 Metal Surfaces
    13. Violation: 168 Premises Identification
    14. Violation: 169 Columns
    15. Violation: 169 Studs
    16. Violation: 169 Structure
    17. Violation: 171 Exterior Walls
    18. Violation: 179 Door Frames
    19. Violation: 179 Windows
    20. Violation: 181 Doors
    21. Violation: 182 Gates
    22. Violation: 183 Structural Members
    23. Violation: 184 Interior Surfaces
    24. Violation: 185 Floors
    25. Inspection: Posting of Hearing Notice Violation: No WIP
    26. Hearing: Initial Hearing Guilty
    27. Inspection: Posting of Judgment Violation: No WIP
    28. Inspection: Reinspection Violation: No WIP

    The city links this case to permit 22-11153-FGAS.

  204. Code enforcement Case 14-05517-MPM Closed

    A hearing was held on 07/31/2014 with a result of "Guilty".

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 167 Exterior Surfaces
    3. Violation: 167 Siding and Masonry
    4. Violation: 168 Premises Identification
    5. Violation: 169 Structure
    6. Violation: 171 Exterior Walls
    7. Violation: 179 Windows
    8. Violation: 181 Doors
    9. Inspection: Reinspection Violation: WIP
    10. Inspection: Posting of Hearing Notice Violation: No WIP
    11. Hearing: Initial Hearing Guilty

    The city links this case to permit 22-11153-FGAS.

  205. Code enforcement Case 13-02887-PNBL Closed

    A hearing was held on 06/11/2013 with a result of "Guilty: Public Nuisance Blight".

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 28-10 Paint / Protective Treatment
    3. Violation: 28-11 Upright Boards / Framing
    4. Violation: 28-11 Studs
    5. Violation: 28-11 Structure
    6. Violation: 28-13 Siding
    7. Violation: 28-13 Exterior Walls
    8. Violation: 28-15 Boarded and Secured
    9. Violation: 28-16 Sanitation of Property and Premises
    10. Violation: 28-20 Rodent Harborage
    11. Violation: 28-26 Porches, Decks, and Balconies
    12. Violation: 28-29 Sills
    13. Violation: 28-29 Windows
    14. Violation: 28-29 Door Frames
    15. Violation: 28-31 Doors
    16. Violation: 28-33 Duty to Remove Trash and Debris
    17. Violation: 28-33 Duty to Mow Grass
    18. Inspection: Posting of Hearing Notice Violation: No WIP
    19. Violation: Interior Walls - Plaster
    20. Violation: 28-10 Paint / Protective Treatment
    21. Violation: 28-11 Structure
    22. Violation: 28-11 Columns
    23. Violation: 28-11 Floor Joists
    24. Violation: 28-11 Floors
    25. Violation: 28-11 Upright Boards / Framing
    26. Violation: 28-11 Studs
    27. Violation: 28-13 Exterior Walls
    28. Violation: 28-13 Siding
    29. Violation: 28-15 Boarded and Secured
    30. Violation: 28-16 Sanitation of Property and Premises
    31. Violation: 28-20 Rodent Harborage
    32. Violation: 28-25 Soffit
    33. Violation: 28-25 Fascia Boards
    34. Violation: 28-26 Stairways and Steps
    35. Violation: 28-26 Porches, Decks, and Balconies
    36. Violation: 28-29 Windows
    37. Violation: 28-29 Door Frames
    38. Violation: 28-29 Sills
    39. Violation: 28-31 Doors
    40. Violation: 28-33 Duty to Remove Trash and Debris
    41. Violation: 28-33 Duty to Mow Grass
    42. Hearing: Initial Hearing Guilty: Public Nuisance Blight
    43. Inspection: Posting of Judgment Violation: No WIP
    44. Inspection: Inspection Violation: No WIP

    The city links this case to permit 22-11153-FGAS.

  206. Code enforcement Case CEHB-11-4261 Closed

    A hearing was held on 01/31/2012 with a result of "Guilty: Public Nuisance".

    1. Inspection: Inspection Violation Unoccupied
    2. Inspection: Inspection Violation Posted No WIP
    3. Hearing: Initial Hearing Reset: Work in Progress
    4. Inspection: Inspection Violation Posted No WIP
    5. Hearing: Reset Hearing Reset: Owner Legal Issue
    6. Inspection: Inspection Violation WIP
    7. Hearing: Reset Hearing Guilty: Public Nuisance

    The city links this case to permit 22-11153-FGAS.

  207. Code enforcement Case HCES-11-05160 Closed

    The case was filed on 06/13/2011 but has since been closed without further action.

    The city links this case to permit 22-11153-FGAS.

  208. Code enforcement Case ENVHADJ-992424F Closed

    The case was filed on 04/10/2009 but has since been closed without further action.

    1. Violation: 167 Exterior Surfaces
    2. Violation: 169 Structure
    3. Violation: 179 Windows
    4. Violation: 181 Doors

    The city links this case to permit 22-11153-FGAS.