Lower Ninth Ward
1236 Alabo Street is in Lower Ninth Ward, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 7 permits on record here; the most recent, a mechanical fuel gas permit, was filed in May 2023. 1 is still open. There were 11 past code enforcement cases, the latest in July 2018, all closed. On this block in the past year: 2 requests to 311 and 3 calls to police.
- Zoning
- HU-RD2
- Historic district
- None
- Council district
- E
- Ward
- 9
- Lot size
- 3,712 sq ft
- Parcel
- 41120943
Everything on record here
18 records, newest first · 1 open
-
Permit Mechanical Fuel Gas Permit Finaled
Installed electric water heater
- Permit
- 23-14151-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $1,500
- Fees
- $20
- Contractor
- Christopher Joseph Deslatte
- Days from application to issue
- 1
- Expires
- Nov 24, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Repair / Replacement / Addition Permit Issued
new construction single family residence wiring job
- Permit
- 22-23989-ERPR
- Type
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $13,500
- Fees
- $157
- Days from application to issue
- 3
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
new construction single family residence wiring job
- Permit
- 22-23989-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $13,500
- Fees
- $157
- Contractor
- James David Pruitt
- Days from application to issue
- 3
- Expires
- Feb 18, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Mechanical HVAC Permit Finaled
gas heat and 2.5 ton air-conditioner install
- Permit
- 22-23983-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $9,300
- Fees
- $70
- Contractor
- James David Pruitt
- Days from application to issue
- 12
- Expires
- Feb 22, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Mechanical Fuel Gas Permit Cancelled
water heater install
- Permit
- 22-19348-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $1
- Fees
- $20
- Contractor
- Christopher Joseph Deslatte
- Days from application to issue
- 7
- Expires
- Jan 5, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Construction Loop Permit Finaled
construction loop
- Permit
- 22-16765-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $13,500
- Fees
- $40
- Contractor
- James David Pruitt
- Days from application to issue
- 7
- Expires
- Dec 13, 2022
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
New construction of a one-story single-family residence on a vacant lot.
- Permit
- 22-04618-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $111,725
- Fees
- $732
- Contractor
- Silva Construction LLC
- Days from application to issue
- 115
- Expires
- Dec 9, 2022
- Application submitted
- Zoning review
- Application review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Code enforcement Case 18-06196-MPM Closed
A hearing was held on 09/29/2020 with a result of "Guilty".
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 159 Sidewalks
- Violation: 160 Weeds and Plant Growth
- Violation: 161 Rodent Harborage
- Inspection: Posting of Hearing Notice Violation: No WIP
- Hearing: Initial Hearing Guilty
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-981043P Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-2000179PB Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-20032300P Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-20041387PR Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-20053715PR Closed
The case was filed on 04/10/2009 but has since been closed without further action.
- Inspection: Inspection Complete
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-2008289PR Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-912202 Closed
The case was filed on 04/10/2009 but has since been closed without further action.
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-921379H Closed
The case was filed on 04/10/2009 but has since been closed without further action.
- Inspection: Inspection Complete
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-931710N Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Hearing: Initial Hearing Found Guilty
- Inspection: Inspection Complete
The city links this case to permit 23-14151-FGAS.
-
Code enforcement Case ENVHADJ-973349P Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 23-14151-FGAS.