Lower Ninth Ward
2516 Delery Street is in Lower Ninth Ward, zoned S-RS (Newer neighborhoods, single-family homes). The city has 6 permits on record here; the most recent, a mechanical fuel gas permit, was filed in November 2024. 5 are still open. On this block in the past year: 8 requests to 311 and 7 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- E
- Ward
- 9
- Lot size
- 6,567 sq ft
- Parcel
- 41121367
Everything on record here
6 records, newest first · 5 open
-
Permit Mechanical Fuel Gas Permit Finaled
Gas vacancy
- Permit
- 24-33762-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $400
- Fees
- $30
- Days from application to issue
- 2
- Expires
- May 7, 2025
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
REWIRE- TAKE OVER JOB FROM REGINALD MCNEIL WHO IS NO LONGER AFFILIATED WITH THIS ADDRESS AS PER OWNER.
- Permit
- 08ELC-26074
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Champ Electric
- Days from application to issue
- 10
-
Permit Electrical Service / Circuit / Feeder Application Acceptance - Approved
REWIRE
- Permit
- 08ELC-11330
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $113
- Contractor
- La-Mac Electric
- Days from application to issue
- 10
-
Permit General Mechanical Meter Release - Released
RLL-F-SMITH-444-4482-RECONNECT-1-WH-CK-1072
- Permit
- 08MCH-07049
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $50
- Contractor
- Your Air Conditioning & Heating Specialist
- Days from application to issue
- 5
-
Permit Construction Loop Application Acceptance - Approved
TEMP POLE
- Permit
- 08ELC-09100
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- La-Mac Electric
- Days from application to issue
- 10
-
Permit Emergency Permit Application Acceptance - Approved No Review
REPAIRS TO A HURRICANE DAMAGED DWELLING
- Permit
- 08BLD-02086
- Type
- Emergency Permit
- Work
- Emergency Permit
- Estimated cost (applicant’s figure)
- $68,000
- Fees
- $390
- Days from application to issue
- 5