Lower Ninth Ward

1806 Flood Street is in Lower Ninth Ward, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 7 permits on record here; the most recent, a mechanical fuel gas permit, was filed in January 2026. 1 is still open. A demolition permit was filed in February 2011. A building here was demolished under the NORA program, completed in April 2011. There was 1 past code enforcement case, the latest in December 2010, all closed. On this block in the past year: 2 requests to 311 and 7 calls to police.

Zoning
HU-RD2
Historic district
None
Council district
E
Ward
9
Lot size
3,947 sq ft
Parcel
41121709

Everything on record here

9 records, newest first · 1 open

  1. Permit Mechanical Fuel Gas Other

    Install electric water heater.

    Permit
    26-00580-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $200
    Fees
    $20
    Contractor
    SBP Real Estate Inc
    Days from application to issue
    63
    Expires
    Sep 12, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Plumbing Permit Other

    Install new sewer and water lines to single family residence.

    Permit
    25-03738-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $150
    Contractor
    Joseph E Monaghan
    Days from application to issue
    0
    Expires
    Aug 5, 2025

    See this permit on One Stop

  3. Permit Mechanical HVAC Other

    Install (1) 2 ton heat pump HVAC in new construction house

    Permit
    25-01873-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $15,600
    Fees
    $65
    Contractor
    The St Bernard Project Inc
    Days from application to issue
    1
    Expires
    Jul 17, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Construction Loop Permit Finaled

    Installing temp pole and needing inspections with third party.

    Permit
    24-11704-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $12,530
    Fees
    $40
    Contractor
    Roy Ellsworth Farthing Jr
    Days from application to issue
    5
    Expires
    Oct 24, 2024
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  5. Permit Electrical Service / Circuit / Feeder Other

    • Permits and inspections with city of New Orleans. • Electrical new construction according drawings dated 1/5/24. • 2020 NEC regulation applied. • 27x, 6" can lights. Owners provide trims. • Dual gfci/ark fault breakers as needed. • Tempoary power pole.

    Permit
    24-10234-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $12,530
    Fees
    $172
    Contractor
    Roy Ellsworth Farthing Jr
    Days from application to issue
    10
    Expires
    Oct 18, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit New Construction Other

    NEW 1,430 SF 3BED 2BATH 1 STORY SINGLE FAMILY HOUSE

    Permit
    24-03574-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $199,799
    Fees
    $1,260
    Contractor
    Hard Hat Construction LLC
    Days from application to issue
    24
    Expires
    Sep 1, 2024
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  7. Demolition NORA demolition Completed
    Program
    NORA
    Units
    1
    Started
    Apr 29, 2011
    Completed
    Apr 29, 2011

    Source: data.nola.gov BlightStatus demolitions (2009–2019, no longer updated)

  8. Permit Demolition Permit Issuance - Active

    DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. NCDC 1/18/11

    Permit
    11BLD-01062
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $145
    Days from application to issue
    0
  9. Code enforcement Case HCES-10-01603 Closed

    The property was inspected on 12/16/2010 with a finding of "Road Home". The file was subsequently closed.

    1. Inspection: Inspection Road Home