Lower Ninth Ward
2409 Jourdan Avenue is in Lower Ninth Ward, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 3 permits on record here; the most recent, a residential permit, was filed in June 2011. 3 are still open. A demolition permit was filed in August 2006. A building here was demolished under the NORA program, completed in October 2011. There was 1 past code enforcement case, the latest in June 2019, all closed. On this block in the past year: 1 request to 311 and 2 calls to police.
- Zoning
- HU-RD2
- Historic district
- None
- Council district
- E
- Ward
- 9
- Lot size
- 4,313 sq ft
- Parcel
- 41122285
Everything on record here
5 records, newest first · 3 open
-
Code enforcement Case 19-06859-MPM Closed
The property was inspected on 06/25/2019 with a finding of "Violation: No WIP". The file was subsequently closed.
- Inspection: Inspection Violation: No WIP
- Violation: 157 Sanitation
- Violation: 159 Sidewalks
- Violation: 160 Weeds and Plant Growth
- Violation: 161 Rodent Harborage
-
Demolition NORA demolition Completed
- Program
- NORA
- Units
- 1
- Started
- Aug 30, 2011
- Completed
- Oct 11, 2011
Source: data.nola.gov BlightStatus demolitions (2009–2019, no longer updated)
-
Permit Residential Permit Issuance Active
PERMIT ISSUED TO DEMOLISH SLAB ONLY
- Permit
- 11BLD-04489
- Type
- Residential
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $5,000
- Fees
- $120
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLISH VACANT RESIDENCE TO GRADE PER OWNERS REQUEST AND DEBRIS REMOVAL WITHIN 72 HOURS OF THE DEMOLITION. A FINAL INSPECTION IS REQUIRED. ANY FURTHER CONSTRUCTION WILL REQUIRE A SEPERATE PERMIT.
- Permit
- 06BLD-08164
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLISH VACANT RESIDENCE TO GRADE PER OWNERS REQUEST AND HAUL AWAY DEBRIS WITHIN 72 HOURS OF DEMOLITION. OUTSIDE OF THE HOUSING CONSERVATION DISTRICT REVIEW COMMITTEE. ANY FURTHER CONSTRUCTION WILL REQUIRE A SEPARATE PERMIT.
- Permit
- 06BLD-04151
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Contractor
- Ecc/Usace
- Days from application to issue
- 5