Lower Ninth Ward

5909 Saint Claude Avenue is in Lower Ninth Ward, zoned HU-MU (Older neighborhoods, walkable mix of shops with homes above). The city has 109 permits on record here; the most recent, an accessory structure permit, was filed in March 2024. 11 are still open. A demolition permit was filed in April 2020. There were 2 past code enforcement cases, the latest in April 2024, all closed. On this block in the past year: 1 request to 311 and 16 calls to police.

Zoning
HU-MU
Historic district
None
Council district
E
Ward
9
Lot size
57,866 sq ft
Parcel
41122875

Everything on record here

111 records, newest first · 11 open

  1. Code enforcement Case 24-03153-MPM Closed

    The case was filed on 04/12/2024 but has since been closed without further action.

    The city links this case to permit 21-10029-SERV.

  2. Permit Accessory Structure Permit Issued

    Building a Pergola with covering and seating. Decorated with native plants and planters and community artwork. This will allow an area for residents to sit outside. City funded project to be installed by volunteers.

    Permit
    24-08090-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $14,000
    Fees
    $190
    Days from application to issue
    49
    Expires
    Nov 8, 2024
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  3. Permit New Construction Permit Cancelled

    The Leona Tate Foundation for Change, Inc. is building an outside covered area for residents to sit. Tables and chairs are included. This project is located behind the building once used as a cafeteria. WITHDRAWN, NEEDS TO BE ACCESSORY PERMIT.

    Permit
    24-05957-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $7,000
    Fees
    $155
    1. Application submitted

    See this permit on One Stop

  4. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Provide new service and branch circuits to feed a multi use building behind the McDonough #19 main building

    Permit
    21-34981-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $70,000
    Fees
    $220
    Contractor
    M. Steven M Ordes
    Days from application to issue
    7
    Expires
    Jun 23, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Street Cut Other

    6" Sewer Service tie-in for new Cafeteria. Service cut will occur on Alabost St. approximately 118' from down stream manhole.

    Permit
    21-32368-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0

    See this permit on One Stop

  6. Permit Mechanical HVAC Permit Issued

    10-TON ROOFTOP UNIT W/20KW HEAT

    Permit
    21-29004-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $42,000
    Fees
    $91
    Contractor
    CDW Services LLC
    Days from application to issue
    1
    Expires
    Apr 22, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Moving Equipment Permit Finaled

    Elevator Installation

    Permit
    21-28983-MOVG
    Type
    Moving Equipment
    Work
    Moving Equipment
    Estimated cost (applicant’s figure)
    $0
    Fees
    $95
    Contractor
    Schindler Elevator Corp
    Days from application to issue
    0
    Expires
    Apr 15, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit Street Cut Other

    Street cut permit for McDonough 19 fire suppression 6 inch water line tap and valve on 1101 Gordon st.

    Permit
    21-11475-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $845
    Contractor
    Battle Reef Contracting, LLC.
    Days from application to issue
    0
    Expires
    Nov 27, 2021

    See this permit on One Stop

  9. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10087-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  10. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10086-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  11. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10085-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  12. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10084-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  13. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10083-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  14. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10082-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  15. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10081-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  16. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10080-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  17. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10079-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  18. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10078-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  19. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10077-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  20. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10076-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  21. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10075-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  22. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10074-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  23. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10073-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  24. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10072-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    100
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  25. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10071-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  26. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10070-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  27. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10063-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  28. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10029-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  29. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10028-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  30. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10027-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  31. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10026-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  32. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10025-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  33. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10030-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    M. Steven M Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  34. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10023-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  35. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10022-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  36. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10020-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  37. Permit Electrical Service / Circuit / Feeder Permit Finaled

    NEW SERVICE 20-02145-RNVS

    Permit
    21-10017-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    103
    Expires
    Jan 21, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  38. Permit Electrical Moving Stair / Dumbwaiter / Manlift Permit Finaled

    ELEVATOR FOR MIXED USE APARTMENTS & OFFICES 20-02145-RNVS

    Permit
    20-45954-MOVS
    Type
    Electrical Moving Stair / Dumbwaiter / Manlift
    Work
    Electrical Moving Stair / Dumbwaiter / Manlift
    Estimated cost (applicant’s figure)
    $0
    Fees
    $60
    Contractor
    Steven M. Ordes
    Days from application to issue
    0
    Expires
    May 9, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

    Placed here by the building address from “5909 St Claude Ave Elevator”.

  39. Permit Electrical Service / Circuit / Feeder Permit Finaled

    20-02145-RNVS NEW SERVICE FOR MIXED USE APARTMENTS & OFFICES 1600 AMPS AND 292 CIRCUITS

    Permit
    20-45863-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $1,396
    Contractor
    Steven M. Ordes
    Days from application to issue
    91
    Expires
    Aug 8, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

    Placed here by the building address from “5909 St Claude Ave FIRE PUMP”.

  40. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38198-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  41. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38196-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  42. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38195-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  43. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38194-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  44. Permit Mechanical Fuel Gas Inspection Phase

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38193-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  45. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38190-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  46. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38188-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  47. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38186-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  48. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38184-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  49. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38181-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  50. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38180-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  51. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38178-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  52. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38176-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  53. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38173-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  54. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38172-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  55. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38170-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  56. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38166-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  57. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38164-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  58. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38162-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  59. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38160-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  60. Permit Mechanical Fuel Gas Permit Finaled

    Install One 40 gallon AO Smith Water Heater

    Permit
    20-38157-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  61. Permit Mechanical Fuel Gas Permit Finaled

    Install one 40 gallon AO Smith Water Heater

    Permit
    20-38155-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    29
    Expires
    Mar 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  62. Permit Mechanical Fuel Gas Permit Finaled

    Install one 40 gallon AO Smith Water Heater

    Permit
    20-38154-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  63. Permit Mechanical Fuel Gas Permit Finaled

    INSTALL ONE 40 GALLON AO SMITH ELECTRIC WATER HEATER

    Permit
    20-38151-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  64. Permit Mechanical Fuel Gas Permit Finaled

    INSTALL 40 GAL AO SMITH ELECTRIC WATER HEATER

    Permit
    20-38147-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $20
    Days from application to issue
    27
    Expires
    Mar 14, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  65. Permit Mechanical HVAC Permit Finaled

    COMMON AREA - SPLIT SYSTEMS

    Permit
    20-36115-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $265,850
    Fees
    $708
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  66. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36114-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  67. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36111-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  68. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36110-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  69. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36109-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  70. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36108-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  71. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36105-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  72. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36104-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  73. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36103-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  74. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36100-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  75. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36097-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  76. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36096-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  77. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36095-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  78. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36094-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  79. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36091-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  80. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36088-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  81. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36087-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  82. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36086-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  83. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36084-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  84. Permit Mechanical HVAC Permit Finaled

    SPLIT SYSTEM

    Permit
    20-36066-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  85. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36064-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  86. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36062-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  87. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36058-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  88. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36056-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  89. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36054-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  90. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36053-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  91. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36050-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  92. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36048-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  93. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36046-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  94. Permit Mechanical HVAC Permit Finaled

    Split System

    Permit
    20-36044-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $20,000
    Fees
    $65
    Contractor
    CDW Services LLC
    Days from application to issue
    2
    Expires
    Jan 31, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  95. Permit Mechanical HVAC Permit Cancelled

    Split Systems

    Permit
    20-35621-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $845,850
    Fees
    $1,684
    Contractor
    CDW Services LLC
    1. Application submitted

    See this permit on One Stop

  96. Permit Mechanical Fuel Gas Permit Cancelled

    25 ELECTRIC WATER HEATERS A.O.SMITH 30 GAL

    Permit
    20-33726-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $491,600
    Fees
    $0
    1. Application submitted

    See this permit on One Stop

  97. Permit Change of Address Permit Issued

    Addressing mixed use 20-02145-RNVS KEEP 5909 St Claude Ave ADD 5909 St Claude Ave Suites 101-104 ADD 5909 St Claude Ave Apts 201-212 ADD 5909 St Claude Ave Apts 301-313 ADD 5910 Marais St ( for cafeteria )

    Permit
    20-29021-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Nov 22, 2020
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

  98. Permit VCC General Work Permit Cancelled

    Interior gut and renovation of existing building to accommodate senior housing apartments and museum exhibition space, a new addition to include elevator and egress stair, and site improvements such as landscaping and parking lot as per plans.

    Permit
    20-25225-VCGEN
    Type
    VCC General Work
    Work
    VCC General Work
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    56
    Expires
    Jan 16, 2021

    See this permit on One Stop

  99. Permit Demolition Other

    This is a demolition permit application to be considered in conjunction with issued Demolition permit 20-01746 and currently pending building permit 20-02145-RNVS. The caretaker cottage at the northwest corner of the site for McDonogh 19 Mixed Use has been deemed non-contributing by the National Register of Historic Place's assessment of the school's campus and has been recommended to be demolished in the project's Building Condition Assessment conducted by Crawford Engineering. It has not been occupied since 2005 at the earliest and was most recently used as an extension of the school building, not a residence. This application for demolition permit is to demolish the caretaker cottage only.

    Permit
    20-24716-DEMO
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $12,000
    Fees
    $655
    Contractor
    CDW Services
    1. Application submitted
    2. Application review

    See this permit on One Stop

  100. Permit Construction Loop Permit Issued

    Provide temp power for demo

    Permit
    20-04630-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Steven M. Ordes
    Days from application to issue
    270
    Expires
    May 16, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  101. Permit Renovation (Structural) Occupancy

    Interior gut and renovation of existing building to accommodate senior housing apartments and museum exhibition space, a new addition to include elevator and egress stair, and site improvements such as landscaping and parking lot as per plans.

    Permit
    20-02145-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $8,300,000
    Fees
    $50,235
    Days from application to issue
    171
    Expires
    Jan 16, 2021
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  102. Permit Interior Demolition Permit Issued

    Interior demolition and access opening

    Permit
    20-01746-DEMI
    Type
    Interior Demolition
    Work
    Interior Demolition
    Estimated cost (applicant’s figure)
    $180,000
    Fees
    $1,140
    Days from application to issue
    8
    Expires
    Jul 31, 2020
    1. Issue date
    2. Application submitted
    3. Application review
    4. Zoning review
    5. Plan review
    6. Permit approved

    See this permit on One Stop

  103. Code enforcement Case 18-05973-MPM Closed

    The property was inspected on 08/22/2018 with a finding of "Violation: No WIP". The file was subsequently closed.

    1. Inspection: Inspection Violation: No WIP
    2. Violation: 157 Sanitation
    3. Violation: 159 Sidewalks
    4. Violation: 160 Weeds and Plant Growth
    5. Violation: 161 Rodent Harborage

    The city links this case to permit 21-32368-RSTC.

  104. Permit Construction Loop Permit Issued

    TEMP POLE- 12-26761

    Permit
    12-28141-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Daryl S. Evans
    Days from application to issue
    0
    Expires
    Apr 23, 2013

    See this permit on One Stop

  105. Permit Renovation (Non-Structural) Permit Issued

    Boarding up windows, cleaning up,fencing, and mold remediation.

    Permit
    12-26761-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $358,000
    Fees
    $1,850
    Contractor
    Christopher Walker
    Days from application to issue
    0
    Expires
    Apr 9, 2013

    See this permit on One Stop

  106. Permit Mechanical Annual Fee Pending
    Permit
    03MCH-07898
    Type
    Mechanical
    Work
    Stationary Equipment Annual
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
  107. Permit Electrical

    INCREASE OF SERVICE SCHOOL EDWARD RAYNER

    Permit
    E01007995
    Type
    Electrical
    Days from application to issue
    0
  108. Permit Mechanical

    INSTALL MECHANICAL EQUIPMENT SCHOOL

    Permit
    M01005243
    Type
    Mechanical
  109. Permit Mechanical

    INSTALL MECHANICAL EQUIPMENT SCHOOL INSTALLATION OF 6-3TON A/C UNITS; 2-2TON UNITS; 1-1/5TON UNIT; TWO 90TON CHILLERS 3- ELECTRIC HEAT DUCTS. BERNARD 271-3431.

    Permit
    M01005214
    Type
    Mechanical
    Days from application to issue
    1
  110. Permit Building

    INTERIOR DEMOLITION SCHOOL INTERIOR DEMOLITION OF EXISTING SCHOOL PERMIT # B01003185 SUBMITTED FOR RENOVATIONS, WORK TO ALSO INCL: DEMO OF (10'X 10') SECTION OF PARK LOT

    Permit
    B01003216
    Type
    Building
    Days from application to issue
    0
  111. Permit Building

    GENERAL REPAIRS SCHOOL MAINT. REPAIRS,LIFE SAFETY,ADA UPGRADES, AIR CONDITIONING AS PER PLANS. WORK TO ALSO INCLUDE PLUMBING, ELECTRICAL, AND MECHANICAL.\\\\\CITY PROJECT/////

    Permit
    B01003185
    Type
    Building
    Days from application to issue
    42