Lower Ninth Ward
1720 Flood Street is in Lower Ninth Ward, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 13 permits on record here; the most recent, an electrical repair / replacement / addition permit, was filed in August 2024. 4 are still open. A demolition permit was filed in October 2006. On this block in the past year: 11 requests to 311 and 13 calls to police.
- Zoning
- HU-RD2
- Historic district
- None
- Council district
- E
- Ward
- 9
- Lot size
- 20,092 sq ft
- Parcel
- 41124092
Everything on record here
13 records, newest first · 4 open
-
Permit Electrical Repair / Replacement / Addition Permit Issued
Install 1-dedicated circuit for sign.
- Permit
- 24-23886-ERPR
- Type
- Electrical Repair / Replacement / Addition
- Work
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $1,375
- Fees
- $43
- Contractor
- Daniel Blake Achord
- Days from application to issue
- 11
- Expires
- Feb 15, 2025
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Electrical Sign Permit Finaled
CONNECT TO EXISTING ELECTRICAL FEED
- Permit
- 23-29313-ESGN
- Type
- Electrical Sign
- Work
- Electrical Sign
- Estimated cost (applicant’s figure)
- $9,961
- Fees
- $40
- Contractor
- A-1 Signs Inc
- Days from application to issue
- 7
- Expires
- Apr 30, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Attached Sign Permit Issued
(detached monument sign) Manufacture and install (1) 4’-0” x 8’-0” D/F LED illuminated sign cabinet with 2’-0” x 4’-0” pole cover, support pole, and foundation.
- Permit
- 23-24168-SATT
- Type
- Attached Sign
- Work
- Attached Sign
- Estimated cost (applicant’s figure)
- $0
- Fees
- $110
- Contractor
- A-1 Signs Inc
- Days from application to issue
- 33
- Expires
- Apr 3, 2024
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
It’s a church and I need a final. Renewing permit see Charles Collins. (Final Walk Through Inspection)
- Permit
- 20-34414-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $1,000
- Fees
- $40
- Contractor
- Wayne Mitchell Preyan Sr.
- Days from application to issue
- 1
- Expires
- Jan 15, 2021
- First inspection
- Application submitted
- Application review
- Permit approved
- Issue date
-
Permit Electrical Service / Circuit / Feeder Permit Cancelled
Renewing of old permit
- Permit
- 20-34188-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $1,000
- Fees
- $160
- Contractor
- Wayne Mitchell Preyan Sr.
- Application submitted
-
Permit Mechanical Fuel Gas Permit Finaled
install electric water heater
- Permit
- 20-24243-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $500
- Fees
- $20
- Days from application to issue
- 3
- Expires
- Oct 6, 2020
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
4 5 ton electric and condensers
- Permit
- 18-39945-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $170
- Days from application to issue
- 56
- Expires
- Jul 31, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
New wiring - new const.
- Permit
- 18-35942-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $331
- Contractor
- Wayne Mitchell Preyan Sr.
- Days from application to issue
- 0
- Expires
- Apr 30, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
Temp Pole.
- Permit
- 18-35131-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Wayne Mitchell Preyan Sr.
- Days from application to issue
- 0
- Expires
- Apr 23, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Renovation (Structural) Occupancy
Renovate church as per plans. Extend permit for 6 months until December 25, 2020.
- Permit
- 18-13850-RNVS
- Type
- Renovation (Structural)
- Work
- Renovation (Structural)
- Estimated cost (applicant’s figure)
- $100,000
- Fees
- $725
- Contractor
- Eugene A Brian,PE
- Days from application to issue
- 421
- Expires
- Dec 20, 2019
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit Renovation (Structural) Permit Issued
Phase II - to enclose existing structure to preserve and protect the steel structure w/ roof of 5400 sqft church. SLAB AND EXTERIOR ENCLOSURE ONLY TO MAKE WEATHERTIGHT. NO USE AND OCCUPANCY.
- Permit
- 17-35290-RNVS
- Type
- Renovation (Structural)
- Work
- Renovation (Structural)
- Estimated cost (applicant’s figure)
- $165,000
- Fees
- $1,050
- Contractor
- Silva Construction LLC, Eugene A Brian,PE
- Days from application to issue
- 23
- Expires
- May 8, 2018
-
Permit New Construction In Review
PHASE I - NEW CONSTRUCTION OF AN OPEN-AIR STEEL STRUCTURE WITH ROOF FOR OUTDOOR GATHERINGS AND RECREATION AS PER PLANS AND BZA 069-12. (RE-SUBDIVISION SHALL BE TIED TO COO)
- Permit
- 12-21580-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $300,000
- Fees
- $2,200
- Contractor
- Fins Construction LLC
-
Permit Demolition State Fire Marshal Approval - Approved
DEMOLISH VACANT CHURCH TO GRADE PER OWNERS REQUEST AND DEBRIS REMOVAL WITHIN 72 HOURS OF THE DEMOLITION. A FINAL INSPECTION IS REQUIRED. A LICENSED PLUMBER MUST SECIRE A SEPARAE PERMIT FROM THE SEWERAGE AND WATER BOARD TO CAP OFF SEWER LINES AND REMOVE WATER METERS PRIOR TO DEMOLITION. ANY FURTHER CONSTRUCTION WILL REQUIRE A SEPARATE PERMIT. DAMAGE ASSESSMENT 77%.
- Permit
- 06COM-02433
- Type
- Demolition
- Work
- NA
- Estimated cost (applicant’s figure)
- $4,500
- Fees
- $100
- Days from application to issue
- 5