Lower Ninth Ward

1537 Saint Maurice Avenue is in Lower Ninth Ward, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 11 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in August 2019. 1 is still open. A demolition permit was filed in October 2006. There is 1 open code enforcement case. On this block in the past year: 8 requests to 311 and 10 calls to police.

Zoning
HU-RD2
Historic district
None
Council district
E
Ward
9
Lot size
4,651 sq ft
Parcel
41124832

Everything on record here

12 records, newest first · 2 open

  1. Code enforcement Case 26-08685-MPM Inspection

    The case was filed on 08/03/2026 and the property is awaiting inspection to proceed further.

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance

    The city links this case to permit 19-24320-SERV.

  2. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Electrical. 072211

    Permit
    19-24320-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $196
    Contractor
    William D Brown
    Days from application to issue
    0
    Expires
    Feb 1, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Electrical. 072211

    Permit
    19-24318-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $196
    Contractor
    William D Brown
    Days from application to issue
    0
    Expires
    Feb 1, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Mechanical Fuel Gas Permit Finaled

    New electric water heater. 1524

    Permit
    19-14596-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $20
    Contractor
    James Arnold
    Days from application to issue
    0
    Expires
    Nov 8, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Mechanical Fuel Gas Permit Finaled

    New electric water heater. 1524

    Permit
    19-14595-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $20
    Contractor
    James Arnold
    Days from application to issue
    0
    Expires
    Nov 8, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Mechanical HVAC Permit Finaled

    3 ton electric heater 3 ton condenser

    Permit
    19-06002-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $65
    Days from application to issue
    48
    Expires
    Oct 11, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  7. Permit Mechanical HVAC Permit Finaled

    3 ton electric heater 3 ton condenser

    Permit
    19-06000-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $3,000
    Fees
    $65
    Days from application to issue
    0
    Expires
    Aug 22, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit Construction Loop Permit Finaled

    Temp pole.

    Permit
    18-35394-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Rafael A. Tejeda
    Days from application to issue
    0
    Expires
    Apr 24, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  9. Permit New Construction Occupancy

    Construct 1320 sq ft 1-story, two-family dwelling as per plans. This application replaces application filed on 8/13/18 - Reference Code # WLIGEQ.

    Permit
    18-27467-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $102,869
    Fees
    $678
    Contractor
    Crescent City Construction and Renovation, Roger Freibert
    Days from application to issue
    38
    Expires
    Mar 27, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  10. Permit Change of Address Permit Issued

    New Construction, Double 18-26246-NEWC Addresses of Record:1537-1539 St Maurice Avenue

    Permit
    18-26816-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Feb 14, 2019
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

  11. Permit New Construction Other

    Construct 1320 sq. ft. 1-story, mixed-use building per plans. Single-family dwelling and Leasing Office; Neighborhood Commercial Establishment.

    Permit
    18-26246-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $178,603
    Fees
    $1,134
    Contractor
    Crescent City Construction and Renovation, Robert Freibert
    1. Application submitted

    See this permit on One Stop

  12. Permit Demolition Certificate of Occupancy - Issued No Meter

    Demolish Structure to grade. All permits issued for demolition require the Contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection.

    Permit
    06BLD-09787
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $125