Lower Ninth Ward

1429 Deslonde Street is in Lower Ninth Ward, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 6 permits on record here; the most recent, a demolition permit, was filed in December 2010. 6 are still open. A demolition permit was filed in December 2010. A building here was demolished under the NORA program, completed in February 2011. On this block in the past year: 6 requests to 311 and 3 calls to police.

Zoning
HU-RD2
Historic district
None
Council district
E
Ward
9
Lot size
3,215 sq ft
Parcel
41125068

Everything on record here

7 records, newest first · 6 open

  1. Demolition NORA demolition Completed
    Program
    NORA
    Units
    1
    Started
    Apr 29, 2011
    Completed
    Feb 15, 2011

    Source: data.nola.gov BlightStatus demolitions (2009–2019, no longer updated)

  2. Permit Demolition Inspection - Completed No Requirements

    DEMOLITION PERMIT ISSUED TO DEMOLISH SLAB ONLY. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. 1429-31 DESLONDE ST.

    Permit
    10BLD-07016
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $120
    Days from application to issue
    0
  3. Permit Demolition Permit Issuance - Active

    DEMOLITION PERMIT ISSUED TO DEMOLISH SLAB ONLY CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. 1429-31 DESLONDE ST.

    Permit
    10BLD-06931
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $120
    Days from application to issue
    0
  4. Permit Demolition Certificate of Occupancy - Issued No Meter

    Demolish Structure to grade. All permits issued for demolition require the Contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. Proof of proper disposal of the debris required at the time of final inspection.

    Permit
    06BLD-10714
    Type
    Demolition
    Work
    Demolition
    Estimated cost (applicant’s figure)
    $10,000
    Fees
    $125
  5. Permit Residential APPROVAL

    demolish two family structure to grade and haul away debris

    Permit
    ACCELA-475
    Type
    Residential
    Work
    Repair
    Estimated cost (applicant’s figure)
    $2,000
  6. Permit Mechanical

    INSTALL MECHANICAL EQUIPMENT DOUBLE RESIDENCE CHANGE GAS WATER HEATER. WILLIAM DAVIS - 833-8570

    Permit
    M01007730
    Type
    Mechanical
    Days from application to issue
    0
  7. Permit Mechanical

    INSTALL MECHANICAL EQUIPMENT DOUBLE RESIDENCE METER OUT OVER SIX MONTHS. WILLIAM DAVIS - 833-8570

    Permit
    M01006433
    Type
    Mechanical
    Days from application to issue
    0