Lower Ninth Ward
5017 North Miro Street is in Lower Ninth Ward, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 8 permits on record here; the most recent, a plumbing permit, was filed in February 2025. 1 is still open. A demolition permit was filed in August 2006. There was 1 past code enforcement case, the latest in June 2018, all closed. On this block in the past year: 3 requests to 311 and 2 calls to police.
- Zoning
- HU-RD2
- Historic district
- None
- Council district
- E
- Ward
- 9
- Lot size
- 4,216 sq ft
- Parcel
- 41127109
Everything on record here
9 records, newest first · 1 open
-
Permit Plumbing Permit Other
Kitchen, laundry , 2 full bath rooms, water and sewer
- Permit
- 23-29556-PLMB
- Type
- Plumbing Permit
- Work
- Plumbing Permit
- Estimated cost (applicant’s figure)
- $0
- Fees
- $70
- Contractor
- Richard J Cancienne
-
Permit Mechanical Fuel Gas Permit Finaled
Install 40-gal electric water heater. Edgar Young 813-0256
- Permit
- 24-17802-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $950
- Fees
- $20
- Contractor
- Edgar NMI Young, Jr.
- Days from application to issue
- 15
- Expires
- Dec 27, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
Installation of a one and a half ton mini split system
- Permit
- 24-05863-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $6,000
- Fees
- $65
- Days from application to issue
- 3
- Expires
- Sep 4, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Plumbing Permit Permit Finaled
New construction
- Permit
- 24-03470-PLMB
- Type
- Plumbing Permit
- Work
- Plumbing Permit
- Estimated cost (applicant’s figure)
- $0
- Fees
- $150
- Contractor
- Jennings Quincy
- Days from application to issue
- 21
- Expires
- Aug 26, 2024
-
Permit Construction Loop Permit Finaled
Temp pole
- Permit
- 23-27656-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $6,000
- Fees
- $40
- Contractor
- Jaime Andres Ordonez
- Days from application to issue
- 4
- Expires
- Apr 13, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Complete wire and low voltage.
- Permit
- 23-27655-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $6,000
- Fees
- $123
- Contractor
- Jaime Andres Ordonez
- Days from application to issue
- 9
- Expires
- Apr 18, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
new 1 story, two bedroom, two bathroom, single family residence. SIP panel construction with painted fiber cement board exterior finish and grade beam foundation.
- Permit
- 22-22148-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $140,000
- Fees
- $900
- Contractor
- Concordia
- Days from application to issue
- 437
- Expires
- Apr 2, 2024
- Application submitted
- Zoning review
- Application review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Code enforcement Case 18-04676-MPM Closed
The case was filed on 06/04/2018 but has since been closed without further action.
The city links this case to permit 23-29556-PLMB.
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLITION OF HURRICANE DAMAGED SINGLE FAMILY DWELLING TO GRADE; CONTRACTOR TO REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS AND TO HAVE A FINAL INSPECTION OF THE SITE
- Permit
- 06BLD-05203
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Days from application to issue
- 5