Bayou St. John
607 North Gayoso Street is in Bayou St. John, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Parkview historic district under partial HDLC control, where demolition needs HDLC review. The city has 7 permits on record here; the most recent, an electrical repair / replacement / addition permit, was filed in January 2012. 7 are still open. There were 4 past code enforcement cases, the latest in April 2009, all closed. On this block in the past year: 0 requests to 311 and 1 call to police.
- Zoning
- HU-RD2
- Historic district
- Parkview (Partial control)
- National Register
- Parkview Historic District
- Council district
- A
- Ward
- 5
- Lot size
- 2,841 sq ft
- Parcel
- 41129074
Everything on record here
11 records, newest first · 7 open
-
Permit Electrical Repair / Replacement / Addition Permit Issued
Work Descripton: REPAIRS Historical Import Type: Permits Electrical Residential Repair-Replacement-Addition User: DMFOLEY Tracking: 86129766502 Status: Permit Issuance Active Status Date: 1/3/2012 12:00:00 AM Owner: Lanier John S III Owner Address: C/O Mr Jorge Castillo 1035 Lake Ave Ste 133, Metairie, LA 70005 Owner Edited By: 1/3/2012 by DMFOLEY
- Permit
- 12ELC-00047
- Type
- Electrical Repair / Replacement / Addition
- Work
- Electrical Repair / Replacement / Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Krajcer Electric LLC
- Days from application to issue
- 0
- Expires
- Jul 3, 2012
-
Permit Electrical Permit Issuance Active
VACANCY
- Permit
- 11ELC-12360
- Type
- Electrical
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
-
Permit Electrical Repair / Replacement / Addition Meter Release - Released
VACANCY
- Permit
- 11ELC-03040
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Pelican Elec Cont
- Days from application to issue
- 0
-
Code enforcement Case ENVHADJ-2002258EH Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 11ELC-03040.
-
Code enforcement Case ENVHADJ-20023189EH Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 11ELC-03040.
-
Code enforcement Case ENVHADJ-20053841SN Closed
The property was inspected on 06/29/2005 with a finding of "Complete". The file was subsequently closed.
- Inspection: Inspection Complete
The city links this case to permit 12ELC-00047.
-
Code enforcement Case ENVHADJ-951714SP Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
reconnect
- Permit
- 06ELC-27737
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Carr's Electric
- Days from application to issue
- 10
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
reconnect
- Permit
- 06ELC-27738
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Carr's Electric
- Days from application to issue
- 10
-
Permit Emergency Permit Application Acceptance - Approved No Review
HURRICANE KATRINA REPAIRS - SHEETROCK, WOOD DAMAGE, ROOF, & PAINTING. (3001 TOULOUSE A,B,C)
- Permit
- 06COM-00918
- Type
- Emergency Permit
- Work
- NA
- Estimated cost (applicant’s figure)
- $20,000
- Fees
- $150
- Days from application to issue
- 5
-
Permit Construction Loop Inspection - Completed
temp pole
- Permit
- 05ELC-03312
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Power House Elect
- Days from application to issue
- 10