Central City

2211 Toledano Street is in Central City, zoned HU-B1A (Older neighborhoods, corner stores and small businesses among homes). The city has 44 permits on record here; the most recent, an electrical vacancy permit, was filed in June 2023. 5 are still open. On this block in the past year: 2 requests to 311 and 21 calls to police.

Zoning
HU-B1A
Historic district
None
National Register
Central City Historic District
Council district
B
Ward
11
Lot size
5,490 sq ft
Parcel
41129094

Everything on record here

44 records, newest first · 5 open

  1. Permit Electrical Vacancy Permit Finaled

    Electrical vacancy

    Permit
    23-15535-EVAC
    Type
    Electrical Vacancy
    Work
    Electrical Vacancy
    Estimated cost (applicant’s figure)
    $350
    Fees
    $40
    Contractor
    Charles Hilliard Scott IV
    Days from application to issue
    6
    Expires
    Dec 13, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Renovation (Non-Structural) Occupancy

    Electrical vacancy

    Permit
    23-12189-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $1,000
    Fees
    $125
    Days from application to issue
    14
    Expires
    Nov 24, 2023
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  3. Permit Mechanical HVAC Permit Issued

    Installation of 5 ton ac and heating system. Electric heat.

    Permit
    20-42964-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $6,500
    Fees
    $76
    Days from application to issue
    1
    Expires
    Apr 8, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  4. Permit Mechanical Fuel Gas Permit Finaled

    Electric water heater

    Permit
    20-41248-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $150
    Fees
    $20
    Days from application to issue
    1
    Expires
    Mar 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Mechanical Fuel Gas Permit Finaled

    Electric water heater

    Permit
    20-41247-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $150
    Fees
    $20
    Days from application to issue
    1
    Expires
    Mar 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Mechanical Fuel Gas Permit Finaled

    Electric water heater

    Permit
    20-41245-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $150
    Fees
    $20
    Days from application to issue
    1
    Expires
    Mar 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Mechanical Fuel Gas Permit Finaled

    New electric water heater

    Permit
    20-41244-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $150
    Fees
    $20
    Days from application to issue
    1
    Expires
    Mar 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit Mechanical Fuel Gas Permit Finaled

    New electric water heater install

    Permit
    20-41242-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $150
    Fees
    $20
    Days from application to issue
    1
    Expires
    Mar 23, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  9. Permit Mechanical HVAC Permit Finaled

    Installation of a 1.5 ton AC and heating system. Electric heat.

    Permit
    20-38363-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    Days from application to issue
    15
    Expires
    Mar 3, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  10. Permit Mechanical HVAC Permit Finaled

    Installation of a 1.5 ton AC and heating system. Electric heat.

    Permit
    20-38361-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    Days from application to issue
    15
    Expires
    Mar 3, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  11. Permit Mechanical HVAC Permit Finaled

    Installation of a 1.5 ton AC and heating system. Electric heat.

    Permit
    20-38359-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    Days from application to issue
    15
    Expires
    Mar 3, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  12. Permit Mechanical HVAC Permit Finaled

    Installation of a 1.5 ton AC and heating system. Electric heat.

    Permit
    20-38358-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    Days from application to issue
    15
    Expires
    Mar 3, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  13. Permit Mechanical HVAC Permit Finaled

    Installation of a 1.5 ton AC and heating system. Electric heat.

    Permit
    20-38354-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    Days from application to issue
    15
    Expires
    Mar 3, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  14. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Electric alterations and repairs. New switches, receptacles and fixtures.

    Permit
    20-38292-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Lopez Reinaldo
    Days from application to issue
    0
    Expires
    Feb 19, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  15. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Electric alterations and repairs. New switches, receptacles and fixtures.

    Permit
    20-38289-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Lopez Reinaldo
    Days from application to issue
    0
    Expires
    Feb 19, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  16. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Electric alterations and repairs. New switches, receptacles and fixtures.

    Permit
    20-38251-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Lopez Reinaldo
    Days from application to issue
    1
    Expires
    Feb 19, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  17. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Electric alterations and repairs. New switches, receptacles and fixtures.

    Permit
    20-38249-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Lopez Reinaldo
    Days from application to issue
    1
    Expires
    Feb 19, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  18. Permit Electrical Repair / Replacement / Addition Permit Finaled

    Electric alterations and repairs. New switches, receptacles and fixtures.

    Permit
    20-38247-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Lopez Reinaldo
    Days from application to issue
    1
    Expires
    Feb 19, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  19. Permit Change of Address Permit Issued

    Update addresses for Apartments Change 2211 Toledano St Apt 1 to 2201 Toledano St Apt 201 (meter 153642947) Change 2211 Toledano St Apt 2 to 2201 Toledano St Apt 202 (meter 153642806) Change 2211 Toledano St Apt 3 to 2201 Toledano St Apt 203 (meter 153642707) Change 2211 Toledano St Apt 4 to 2201 Toledano St Apt 204 (meter 153766654) Change 2211 Toledano St Apt 5 to 2201 Toledano St Apt 205 (meter 153642632)

    Permit
    20-37369-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Feb 10, 2021
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

    Placed here by the building address from “2201 Toledano St Apt 201-Apt 205”.

  20. Permit Street Cut Other
    Permit
    20-30916-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $392
    Days from application to issue
    2
    Expires
    Dec 12, 2020

    See this permit on One Stop

  21. Permit Mechanical Fuel Gas Permit Finaled

    New electric water heater install.

    Permit
    20-03411-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $20
    Contractor
    William Leroy Hoffman, Jr
    Days from application to issue
    201
    Expires
    Feb 28, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  22. Permit Mechanical Fuel Gas Permit Finaled

    New electric water heater.

    Permit
    20-03413-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $20
    Contractor
    William Leroy Hoffman, Jr
    Days from application to issue
    277
    Expires
    May 12, 2021
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  23. Permit Electrical Repair / Replacement / Addition In Review

    Electric alterations and repairs. New switches, receptacles and fixtures. NEED GIS AND CHECK SCOPE OF WORK 5.5.20 applying for 4 apts in additon to the 1 already issued building permit states 4 units total plans show 8 Entergy only showing record of 1 com unit

    Permit
    19-38449-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Reinaldo Lopez
    1. Application submitted
    2. Application review

    See this permit on One Stop

  24. Permit Electrical Repair / Replacement / Addition In Review

    Electric alterations and repairs. New switches, receptacles and fixtures. NEED GIS AND CHECK SCOPE OF WORK 5.5.20 applying for 4 apts in additon to the 1 already issued building permit states 4 units total plans show 8 Entergy only showing record of 1 com unit

    Permit
    19-38448-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Reinaldo Lopez
    1. Application submitted
    2. Application review

    See this permit on One Stop

  25. Permit Electrical Repair / Replacement / Addition In Review

    Electric alterations and repairs. New switches, receptacles and fixtures. NEED GIS AND CHECK SCOPE OF WORK 5.5.20 applying for 4 apts in additon to the 1 already issued building permit states 4 units total plans show 8 Entergy only showing record of 1 com unit

    Permit
    19-38440-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Reinaldo Lopez
    1. Application submitted
    2. Application review

    See this permit on One Stop

  26. Permit Electrical Repair / Replacement / Addition In Review

    Electric alterations and repairs. New switches, receptacles and fixtures. NEED GIS AND CHECK SCOPE OF WORK 5.5.20 applying for 4 apts in additon to the 1 already issued building permit states 4 units total plans show 8 Entergy only showing record of 1 com unit

    Permit
    19-38437-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $1,500
    Fees
    $96
    Contractor
    Reinaldo Lopez
    1. Application submitted
    2. Application review

    See this permit on One Stop

  27. Permit Mechanical HVAC Permit Cancelled

    Installation of 1.5 ton AC and heating system. Electric heat.

    Permit
    19-38434-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    1. Application submitted

    See this permit on One Stop

  28. Permit Mechanical HVAC Permit Cancelled

    Installation of 1.5 ton AC and heating system. Electric heat.

    Permit
    19-38431-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    1. Application submitted

    See this permit on One Stop

  29. Permit Mechanical HVAC Permit Cancelled

    Installation of 1.5 ton AC and heating system. Electric heat.

    Permit
    19-38430-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    1. Application submitted

    See this permit on One Stop

  30. Permit Mechanical HVAC Permit Cancelled

    Installation of 1.5 ton AC and heating system. Electric heat.

    Permit
    19-38426-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    1. Application submitted

    See this permit on One Stop

  31. Permit Mechanical HVAC Permit Cancelled

    Installation of 1.5 ton AC and heating system. Electric heat.

    Permit
    19-38422-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $65
    1. Application submitted

    See this permit on One Stop

  32. Permit Electrical Repair / Replacement / Addition Permit Issued

    Electric alterations and repairs; replace fixtures.

    Permit
    19-36875-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $58
    Contractor
    Reinaldo Lopez
    Days from application to issue
    14
    Expires
    Jun 2, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  33. Permit Mechanical HVAC Permit Finaled

    Installation of 2 ton ac and heating system. Electric heat.

    Permit
    19-36873-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $3,500
    Fees
    $65
    Days from application to issue
    135
    Expires
    Oct 1, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. First inspection
    5. Issue date

    See this permit on One Stop

  34. Permit Mechanical HVAC Permit Cancelled

    Installation of 5 ton ac and heating system. Electric heat.

    Permit
    19-36872-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $6,500
    Fees
    $71
    1. Application submitted

    See this permit on One Stop

  35. Permit Electrical Service / Circuit / Feeder Permit Cancelled

    Rewire commercial space according to plans. New 200 service 18 circuits CHECK SCOPE OF WORK AND NEEDS GIS

    Permit
    19-36871-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $7,000
    Fees
    $154
    Contractor
    Reinaldo Lopez
    Days from application to issue
    14
    Expires
    Jun 2, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  36. Permit Mechanical HVAC Permit Finaled

    Installation of 2 ton ac and heating system. electric heat.

    Permit
    19-36869-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $3,500
    Fees
    $65
    Days from application to issue
    141
    Expires
    Oct 7, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  37. Permit Electrical Repair / Replacement / Addition Permit Issued

    Electric alterations and repairs; replace fixtures.19-14052-RNVN

    Permit
    19-36865-ERPR
    Type
    Electrical Repair / Replacement / Addition
    Work
    Electrical Repair / Replacement / Addition
    Estimated cost (applicant’s figure)
    $2,500
    Fees
    $58
    Contractor
    Reinaldo Lopez
    Days from application to issue
    140
    Expires
    Oct 6, 2020
    1. Application submitted
    2. First inspection
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  38. Permit Renovation (Structural) Occupancy

    Non-structural renovation to a single family residence consisting of HVAC, Electrical, Plumbing (all under $15,000). Updates to interior finishes repair windows and doors as needed. Exterior paint, roof as needed, exterior framing as needed.

    Permit
    19-14044-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $36,915
    Fees
    $245
    Contractor
    Webre Construction, LLC
    Days from application to issue
    25
    Expires
    Dec 28, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  39. Permit Renovation (Non-Structural) Occupancy

    Mixed use commercial ground floor and residential 2nd floor and attic/loft - 4 units total non-structural. renovation consists of HVAC, Plumbing, and Electrical not to exceed $15,000 for commercial and residential areas. Non-structural commercial renovation consists of carpentry, sheetrock repair, removal of flooring to expose original floors, refinish exposed concrete floors, update HVAC, plumbing and electrical in commercial space on first floor. Residential units will receive updates to interior finishes, retain and repair doors and windows as needed.

    Permit
    19-14056-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $85,876
    Fees
    $576
    Contractor
    Webre Construction, LLC
    Days from application to issue
    86
    Expires
    Feb 16, 2020
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  40. Permit Renovation (Non-Structural) Occupancy

    Non-structural renovation to a single family residence to include Electrical, HVAC, and plumbing (not to exceed $15,000). Updates to interior finishes, exterior paint, repairs to siding as needed, and roof as needed.

    Permit
    19-14052-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $38,222
    Fees
    $255
    Contractor
    Webre Construction, LLC
    Days from application to issue
    37
    Expires
    Dec 28, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  41. Permit Electrical Vacancy Permit Issued

    VACANCY

    Permit
    14-02472-EVAC
    Type
    Electrical Vacancy
    Work
    Electrical Vacancy
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Patrick Mel Thomas
    Days from application to issue
    0
    Expires
    Jul 22, 2014

    See this permit on One Stop

  42. Permit General Mechanical Inspection - Completed

    rll-k-boissiere-615-1407-reconnect-ck-6996

    Permit
    10MCH-00625
    Type
    General Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $30
    Contractor
    K & B Contractors
    Days from application to issue
    5
  43. Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved

    VACANCY

    Permit
    10ELC-00809
    Type
    Electrical Repair / Replacement / Addition
    Work
    Repair-Replacement-Addition
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Patrick Thomas
    Days from application to issue
    10
  44. Permit Building

    HOME BASED BUSINESS HOME BASED BUSINESS CERTIFICATE OF OCCUPANCY FOR HOME BASED BUSINESS "BOB'S PAINTING" C-7890

    Permit
    B96002261
    Type
    Building