East Carrollton

1532 Short Street is in East Carrollton, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Carrollton historic district under partial HDLC control, where demolition needs HDLC review. The city has 3 permits on record here; the most recent, a mechanical fuel gas permit, was filed in October 2019. On this block in the past year: 1 request to 311 and 0 calls to police.

Zoning
HU-RD2
Historic district
Carrollton (Partial control)
National Register
Carrollton Historic District
Council district
A
Ward
16
Lot size
5,397 sq ft
Parcel
41133628

Everything on record here

3 records, newest first

  1. Permit Mechanical Fuel Gas Permit Cancelled

    Gas Line 65’ 1”-1/4

    Permit
    19-34228-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $1,000
    Fees
    $15
    1. Application submitted

    See this permit on One Stop

  2. Permit Permanent Generator Permit Issued

    INSTALLING 22KW PERMANENT GENERATOR AT RESIDENCE // LOAD SHEET AND CONTRACT ATTACHED

    Permit
    19-32876-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $6,500
    Fees
    $76
    Contractor
    Brandon Augustus Francois
    Days from application to issue
    0
    Expires
    Apr 15, 2020
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  3. Permit Renovation (Non-Structural) Other

    INSTALLATION OF 22KW GENERATOR WITH ELECTRICAL SYSTEM ALTERATIONS AND GAS LINE EXTENSION TO MAKE UNIT COMPATIBLE FOR OPERATION AT RESIDENCE. >>> SIGNED CONTRACT & SITE PLAN ATTACHED <<<

    Permit
    19-31572-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $11,800
    Fees
    $120
    Contractor
    B Powered Electric LLC
    Days from application to issue
    12
    Expires
    Apr 15, 2020
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop