Leonidas
1018 Dublin Street is in Leonidas, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Carrollton historic district under partial HDLC control, where demolition needs HDLC review. The city has 3 permits on record here; the most recent, a permanent generator permit, was filed in December 2022. 1 is still open. On this block in the past year: 3 requests to 311 and 1 call to police.
- Zoning
- HU-RD2
- Historic district
- Carrollton (Partial control)
- National Register
- Carrollton Historic District
- Council district
- A
- Ward
- 17
- Lot size
- 8,169 sq ft
- Parcel
- 41134688
Everything on record here
3 records, newest first · 1 open
-
Permit Permanent Generator Permit Finaled
Install 24KW generator with a 200 amp ATS, all electrical and connections
- Permit
- 22-36136-EGEN
- Type
- Permanent Generator
- Work
- Permanent Generator
- Estimated cost (applicant’s figure)
- $18,487
- Fees
- $100
- Contractor
- Barry E. Couvillion
- Days from application to issue
- 4
- Expires
- Jun 6, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Finaled
Install 24KW generator all gas work and connections
- Permit
- 22-36135-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $18,487
- Fees
- $80
- Days from application to issue
- 4
- Expires
- Jun 6, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Accessory Structure Permit Issued
Install 24KW generator with a 200 amp ATS. Generator will be set on a stand 3 ft off ground. Unit will be 8ft off back property line, 5 ft off right property line, and over 20ft from house. Unit will be cleared of all windows, doors and vents
- Permit
- 22-34510-ACCS
- Type
- Accessory Structure
- Work
- Accessory Structure
- Estimated cost (applicant’s figure)
- $18,487
- Fees
- $215
- Days from application to issue
- 17
- Expires
- Jun 2, 2023
- Application submitted
- Zoning review
- Application review
- Plan review
- Permit approved
- Issue date
- First inspection