East Carrollton
7707 Plum Street is in East Carrollton, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Carrollton historic district under partial HDLC control, where demolition needs HDLC review. The city has 3 permits on record here; the most recent, a permanent generator permit, was filed in November 2022. 1 is still open. On this block in the past year: 11 requests to 311 and 1 call to police.
- Zoning
- HU-RD2
- Historic district
- Carrollton (Partial control)
- National Register
- Carrollton Historic District
- Council district
- A
- Ward
- 16
- Lot size
- 3,774 sq ft
- Parcel
- 41137766
Everything on record here
3 records, newest first · 1 open
-
Permit Permanent Generator Permit Finaled
Install of 18kW natural gas emergency whole home generator and a 100 amp transfer switch. Generator will be set on 18in high stand.
- Permit
- 22-35214-EGEN
- Type
- Permanent Generator
- Work
- Permanent Generator
- Estimated cost (applicant’s figure)
- $16,406
- Fees
- $73
- Contractor
- Jeremiah Alexander Johnson
- Days from application to issue
- 45
- Expires
- Jul 6, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Finaled
Install of 18kW natural gas emergency whole home generator and a 100 amp transfer switch. Generator will be set on 18in high stand.
- Permit
- 22-35206-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $16,406
- Fees
- $50
- Contractor
- Jeremiah Alexander Johnson
- Days from application to issue
- 0
- Expires
- May 22, 2023
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Accessory Structure Permit Issued
Install of 18kW natural gas emergency whole home generator and a 200 amp transfer switch. Generator will be set on 18in high stand.
- Permit
- 22-33875-ACCS
- Type
- Accessory Structure
- Work
- Accessory Structure
- Estimated cost (applicant’s figure)
- $16,406
- Fees
- $205
- Contractor
- Ready Power LLC
- Days from application to issue
- 14
- Expires
- May 22, 2023
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection