Old Aurora

2611 Danbury Drive is in Old Aurora, zoned S-RS (Newer neighborhoods, single-family homes). The city has 4 permits on record here; the most recent, a residential re-roofing permit, was filed in May 2026. On this block in the past year: 5 requests to 311 and 4 calls to police.

Zoning
S-RS
Historic district
None
Council district
C
Ward
15
Lot size
8,010 sq ft
Parcel
41139405

Everything on record here

4 records, newest first

  1. Permit Residential Re-Roofing Other

    remove all layers of existing roof to expose decking, Remove the existing couplola and set on the ground in the back, Install a fully adhered secondary water barrier membrane (ice and water shield) over the entire roof deck in place of the one layer of felt, install new drip edge around entire perimeter of roof, install precut starter strips on the perimeter of the roof, Install the Class 4 Impact Rated Atlas Pinnacle lifetime limited warranted architectural shingle according to the manufacturers specifications. (see manufacturer for warranty regarding the shingles), Install the Atlas Procut Hip and Ridge shingles on all hips and ridges according to the manufactures specifications, replace all lead flanges and galvanized jack and caps as needed, reuse all existing flashing, Remove the existing power vent. Install 1 new wind turbine in place of the power vent, *Extra - Flashing Replacement - Remove the necessary siding at roof level, replace the existing flashings with a 26 gauge unpainted galvanized wall and apron flashing, and price accordingly. Reinstall existing siding. If unable to reinstall, replace to match as close as possible and price accordingly PHOTOS REQUIRED 4 geotagged photos (one from each side) showing: Removal of existing roof material Installation of water intrusion resistant underlayment Installation of the drip-edge and flashing Installation of shingles or metal panels Once all applicable photos have been uploaded, please email Inspec

    Permit
    26-13768-ROOF
    Type
    Residential Re-Roofing
    Work
    Residential Re-Roofing
    Estimated cost (applicant’s figure)
    $0
    Fees
    $60
    Contractor
    Robertson Roofing and Siding, Inc
    Days from application to issue
    7
    Expires
    Nov 13, 2026
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Permanent Generator Permit Issued

    Installing a 22 KW generator with 150 amp Transfer Switch, make all connections

    Permit
    18-13182-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $9,832
    Fees
    $88
    Contractor
    Barry E. Couvillion
    Days from application to issue
    0
    Expires
    Oct 19, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    Installation of a 22 KW air cooled generator with all gas work from meter to generator

    Permit
    18-13174-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $9,832
    Fees
    $80
    Contractor
    Barry E. Couvillion
    Days from application to issue
    0
    Expires
    Oct 19, 2018
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Accessory Structure Occupancy

    Installation of 22kw generator that will be on a stand 30 inches off the ground that is higher than the finish floor of the house, We will be doing all electrical and gas work for installation of unit per sketch.

    Permit
    18-12112-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $9,832
    Fees
    $110
    Contractor
    Barry E. Couvillion
    Days from application to issue
    8
    Expires
    Oct 19, 2018
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Permit approved
    5. Issue date
    6. First inspection