Old Aurora

1900 Holiday Drive is in Old Aurora, zoned S-RS (Newer neighborhoods, single-family homes). The city has 3 permits on record here; the most recent, a mechanical fuel gas permit, was filed in June 2025. 1 is still open. On this block in the past year: 7 requests to 311 and 5 calls to police.

Zoning
S-RS
Historic district
None
Council district
C
Ward
15
Lot size
10,125 sq ft
Parcel
41139883

Everything on record here

3 records, newest first · 1 open

  1. Permit Mechanical Fuel Gas Other

    Installation of a whole home generator with a 200 amp transfer switch

    Permit
    25-18662-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $13,855
    Fees
    $50
    Contractor
    Wayne Jeffery Erdman
    Days from application to issue
    6
    Expires
    Dec 24, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Other

    Installation of a whole home generator with a 200 amp transfer switch

    Permit
    25-18660-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $13,855
    Fees
    $106
    Contractor
    Wayne Jeffery Erdman
    Days from application to issue
    1
    Expires
    Dec 19, 2025
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Accessory Structure Permit Issued

    Installation of a whole home 24kW generator with a 200 amp transfer switch to a single family home. To be done as per scope.

    Permit
    25-14469-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $13,055
    Fees
    $190
    Contractor
    Wayne Jeffery Erdman
    Days from application to issue
    37
    Expires
    Dec 18, 2025
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop