242 Abalon Court is in Whitney, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). The city has 7 permits on record here; the most recent, a mechanical fuel gas permit, was filed in June 2019. 2 are still open. On this block in the past year: 16 requests to 311 and 14 calls to police.

Zoning
HU-RD1
Historic district
None
Council district
C
Ward
15
Lot size
6,506 sq ft
Parcel
41140716

Everything on record here

7 records, newest first · 2 open

  1. Permit Mechanical Fuel Gas Permit Finaled

    New gas lines, tankless water heater

    Permit
    19-18044-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    James Arnold
    Days from application to issue
    0
    Expires
    Dec 4, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical HVAC Permit Finaled

    (1) 3 Ton - Gas; (1) 1.5 Ton-Gas

    Permit
    19-04130-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $12,500
    Fees
    $100
    Contractor
    MKRED Realty
    Days from application to issue
    0
    Expires
    Aug 7, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Construction Loop Permit Finaled

    Temporary pole.

    Permit
    18-40095-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $0
    Fees
    $40
    Contractor
    Nguyen DU Du Hai
    Days from application to issue
    0
    Expires
    Jun 6, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Electrical Service / Circuit / Feeder Permit Finaled

    New Construction.

    Permit
    18-40094-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $0
    Fees
    $166
    Contractor
    Nguyen DU Du Hai
    Days from application to issue
    0
    Expires
    Jun 6, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit New Construction Occupancy

    Single Family New Construction Home 2050 sq ft. living

    Permit
    18-34568-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $270,675
    Fees
    $1,686
    Contractor
    John Dalton, MKRed Build llc
    Days from application to issue
    48
    Expires
    Jun 4, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  6. Permit Building

    CERT. OF OCCUPANCY-NO WORK TO BE DONE CONSTRUCTION TRAILER CERTIFICATE OF USE & OCCUPANCY TO ALLOW A TEMPORARY CONSTRUCTION TRAILER FOR THE DURATION OF THE STREET IMPROVEMENT PROJECT.

    Permit
    B02005991
    Type
    Building
  7. Permit Electrical

    ELECTRICAL CONSTRUCTION LOOP CONSTRUCTION TRAILER MICHAEL REAVES

    Permit
    E02009928
    Type
    Electrical
    Days from application to issue