East Carrollton

7722 Hampson Street is in East Carrollton, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Carrollton historic district under partial HDLC control, where demolition needs HDLC review. The city has 3 permits on record here; the most recent, a mechanical fuel gas permit, was filed in July 2022. 1 is still open. On this block in the past year: 5 requests to 311 and 1 call to police.

Zoning
HU-RD1
Historic district
Carrollton (Partial control)
National Register
Carrollton Historic District
Council district
A
Ward
16
Lot size
8,712 sq ft
Parcel
41141112

Everything on record here

3 records, newest first · 1 open

  1. Permit Mechanical Fuel Gas Permit Finaled

    Run gas line from meter through attic and to generator approximately 70 ft

    Permit
    22-22143-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,600
    Fees
    $80
    Days from application to issue
    12
    Expires
    Feb 3, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Permanent Generator Permit Finaled

    Electrical installation and wiring for 24kw home generator with automatic transfer switch

    Permit
    22-10386-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $2,200
    Fees
    $103
    Contractor
    Herbert Willie Hartman III
    Days from application to issue
    4
    Expires
    Oct 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Accessory Structure Permit Issued

    Installation of home Generator

    Permit
    21-22615-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $15,725
    Fees
    $140
    Contractor
    Hebert Willie Hartman III
    Days from application to issue
    71
    Expires
    Apr 14, 2022
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop