Black Pearl
519 Adams Street is in Black Pearl, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). It is in the Carrollton historic district under partial HDLC control, where demolition needs HDLC review. The city has 5 permits on record here; the most recent, a general mechanical permit, was filed in April 2013. 3 are still open.
- Zoning
- HU-RD2
- Historic district
- Carrollton (Partial control)
- National Register
- Carrollton Historic District
- Council district
- A
- Ward
- 16
- Lot size
- 4,548 sq ft
- Parcel
- 41141956
Everything on record here
5 records, newest first · 3 open
-
Permit General Mechanical Permit Finaled
rll-lanze-415-5679-out-6-months-ck-6265
- Permit
- 13-13150-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Lance Resendez
- Days from application to issue
- 1
- Expires
- Oct 30, 2013
-
Permit General Mechanical In Review
rll-lance-415-5679-out-6-months-ck-6265
- Permit
- 13-13151-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Lance Michael Resendez
-
Permit Mechanical Application Approved
l.j.c. david lambert tele. 915 6111 ck.4614,1-4ton a.c. split system w/gas w.a.f.
- Permit
- 07MCH-05383
- Type
- Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $70
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
AFTER HOURS
- Permit
- 07ELC-05886
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $150
- Contractor
- Malone Electrical
- Days from application to issue
- 10
-
Permit Electrical Repair / Replacement / Addition Application Acceptance - Approved
RECONNECT
- Permit
- 07ELC-05888
- Type
- Electrical Repair / Replacement / Addition
- Work
- Repair-Replacement-Addition
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- Malone Electrical
- Days from application to issue
- 10