Old Aurora

3611 Rue Nichole is in Old Aurora, zoned S-RS (Newer neighborhoods, single-family homes). The city has 3 permits on record here; the most recent, a permanent generator permit, was filed in November 2023. 1 is still open. On this block in the past year: 6 requests to 311 and 2 calls to police.

Zoning
S-RS
Historic district
None
Council district
C
Ward
15
Lot size
7,233 sq ft
Parcel
41144289

Everything on record here

3 records, newest first · 1 open

  1. Permit Permanent Generator Permit Finaled

    Installing a 24kW Generac Generator and a 200 amp transfer switch for emergency backup power.

    Permit
    23-31441-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $17,100
    Fees
    $103
    Contractor
    Jeremiah Alexander Johnson
    Days from application to issue
    7
    Expires
    May 21, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Permit Finaled

    Installing a 24kW Generac Generator and a 200 amp transfer switch for emergency backup service.

    Permit
    23-31432-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $17,100
    Fees
    $80
    Contractor
    Ready Power, LLC
    Days from application to issue
    1
    Expires
    May 15, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Accessory Structure Permit Issued

    Installing a 24kW Generac Generator and a 200 amp transfer switch for emergency backup power.

    Permit
    23-30517-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $17,100
    Fees
    $210
    Contractor
    Ready Power, LLC, Ready Power LLC
    Days from application to issue
    7
    Expires
    May 13, 2024
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop