Read Blvd East

10101 Dwyer Road is in Read Blvd East, zoned C-2 (Auto-oriented commercial for large stores and strip centers along major roads). The city has 9 permits on record here; the most recent, a mow to own program permit, was filed in April 2021. 8 are still open. A demolition permit was filed in August 2009. There is 1 open code enforcement case. On this block in the past year: 4 requests to 311 and 2492 calls to police.

Zoning
C-2
Historic district
None
Council district
E
Ward
9
Lot size
58,373 sq ft
Parcel
41147180

Everything on record here

11 records, newest first · 9 open

  1. Code enforcement Case 26-00222-MPM Inspection

    The case was filed on 01/07/2026 and the property is awaiting inspection to proceed further.

    1. Inspection
    2. Title Research
    3. Hearing
    4. Judgment
    5. In Compliance

    The city links this case to permit 21-10861-MOWN.

  2. Permit Mow to Own Program Permit Cancelled

    My home is on 5025 Schindler drive right next to the open field on Dwyer I don’t know the address by it being open land

    Permit
    21-10861-MOWN
    Type
    Mow to Own Program
    Work
    Mow to Own Program
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0

    See this permit on One Stop

  3. Code enforcement Case 15-06172-MPM Closed

    The property was inspected on 07/31/2015 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 21-10861-MOWN.

  4. Permit Mechanical Annual Renewal Pending

    7TH DISTRICT POLICE STATION//(11/29/2013)ANN ELEV INSP//

    Permit
    11MCH-09505
    Type
    Mechanical
    Work
    Moving Equipment Annual
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
  5. Permit Mechanical Inspection Pending

    ajm311, ck 1889 e.t. 416-7550 2-40ton chillers

    Permit
    11MCH-06500
    Type
    Mechanical
    Work
    General Mechanical
    Estimated cost (applicant’s figure)
    $0
    Fees
    $377
  6. Permit Electrical Moving Stair / Dumbwaiter / Manlift Permit Issuance - Active

    ELEVATOR

    Permit
    11ELC-01514
    Type
    Electrical Moving Stair / Dumbwaiter / Manlift
    Work
    Elev.-Mov.Stair-Dmbwtr-Manlift
    Estimated cost (applicant’s figure)
    $0
    Fees
    $60
    Contractor
    Robin Services Inc
    Days from application to issue
    0
  7. Permit Moving Equipment Certificate Of Completion - Issued No Meter

    install 1-3 stop elev. ck#'s 10917277,10920071

    Permit
    11MCH-00022
    Type
    Moving Equipment
    Work
    Elevators-Moving Equipment
    Estimated cost (applicant’s figure)
    $0
    Fees
    $95
    Contractor
    Thyssenkrupp
    Days from application to issue
    5
  8. Permit Electrical Service / Circuit / Feeder Permit Issuance - Active

    NEW CONSTRUCTION- 09COM-01239

    Permit
    10ELC-10021
    Type
    Electrical Service / Circuit / Feeder
    Work
    Service-Circuits-Feeders
    Estimated cost (applicant’s figure)
    $0
    Fees
    $775
    Contractor
    Achary Electric LLC
    Days from application to issue
    0
  9. Permit New Construction Permit Issuance - Active

    Construction of new 7th District Police Station, as per plans.

    Permit
    09COM-01239
    Type
    New Construction
    Work
    NA
    Estimated cost (applicant’s figure)
    $5,322,500
    Fees
    $-22,062
    Days from application to issue
    200
  10. Permit Demolition Application Acceptance - Approved No Review

    DEMOLISH COMMERCIAL BUILDING TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. NOPD 7TH DISTRICT.

    Permit
    09COM-00987
    Type
    Demolition
    Work
    NA
    Estimated cost (applicant’s figure)
    $50,000
    Fees
    $325
    Days from application to issue
    5
  11. Permit Electrical

    ALTERATION POLICE STATION HENRY ROCKER

    Permit
    E01009146
    Type
    Electrical
    Days from application to issue
    0