St. Thomas Dev
643 Saint Mary Street is in St. Thomas Dev, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 6 permits on record here; the most recent, a mechanical fuel gas permit, was filed in November 2018. 3 are still open. On this block in the past year: 1 request to 311 and 7 calls to police.
- Zoning
- HU-RD2
- Historic district
- None
- National Register
- Lower Garden District
- Council district
- B
- Ward
- 10
- Lot size
- 1,281 sq ft
- Parcel
- 41180567
Everything on record here
6 records, newest first · 3 open
-
Permit Mechanical Fuel Gas Permit Issued
electric water heater
- Permit
- 18-37083-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $750
- Fees
- $20
- Days from application to issue
- 1
- Expires
- May 8, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
New electrical with service.
- Permit
- 18-23308-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $157
- Contractor
- Rafael A. Tejeda
- Days from application to issue
- 0
- Expires
- Jan 16, 2019
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
TEMP POLE 18-13123-NEWC
- Permit
- 18-13123-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Rafael A. Tejeda Sr.
- Days from application to issue
- 0
- Expires
- Nov 9, 2018
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
Construct a 2-story 1085 sq ft 1/2 of a party-wall double as per plans.
- Permit
- 18-13123-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $108,500
- Fees
- $714
- Contractor
- Crescent City Construction and Renovation, Roger Freibert
- Days from application to issue
- 18
- Expires
- Nov 7, 2018
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Permit Issuance - Active
NEW CONSTRUCTION OF HALF OF A PARTY WALL DOUBLE (TYPE J). SUPPLEMENT TO 05BLD-01598
- Permit
- 10BLD-07297
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $68,820
- Fees
- $-340
- Contractor
- Hci Construction & Design
- Days from application to issue
- 0
-
Permit New Construction Permit Issuance - Active
New Construction of a 1/2 Party Wall Double,Building Type "J",Residence for Sale as per Plans and BZA.Dkt.#75/04.Fema Flood Zone:B.
- Permit
- 05BLD-01598
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $69,000
- Fees
- $464
- Contractor
- Kb Home Shaw Louisiana LLC
- Days from application to issue
- 40