West End
211 22nd Street is in West End, zoned S-LRS1 (Lake area single-family homes). The city has 6 permits on record here; the most recent, a mechanical permit, was filed in July 2011. 6 are still open. A demolition permit was filed in September 2009. On this block in the past year: 8 requests to 311 and 0 calls to police.
- Zoning
- S-LRS1
- Historic district
- None
- Council district
- A
- Ward
- 17
- Lot size
- 4,596 sq ft
- Parcel
- 41181349
Everything on record here
6 records, newest first · 6 open
-
Permit Mechanical Permit Issuance Active
David Carter check# 11011 gas line, gas water heater
- Permit
- 11MCH-05388
- Type
- Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $35
-
Permit Mechanical Permit Issuance Active
INSTALL GAS WAF AND A\C.. *11BLD-02821 WESLEY RUFFINO (#6036)
- Permit
- 11MCH-04921
- Type
- Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $70
-
Permit Electrical Service / Circuit / Feeder Permit Issuance - Active
NEW CONSTRUCTION- 11BLD-02821
- Permit
- 11ELC-04730
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $190
- Contractor
- B & D Electric Co. Of Baton Rouge, Inc.
- Days from application to issue
- 0
-
Permit Construction Loop Permit Issuance - Active
TEMP POLE- 11BLD-02821
- Permit
- 11ELC-04646
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $230
- Contractor
- B & D Electric Co. Of Baton Rouge, Inc.
- Days from application to issue
- 0
-
Permit New Construction Certificate of Occupancy - Issued w/Meter
NEW CONSTRUCTION OF A 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AS PER PLANS.
- Permit
- 11BLD-02821
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $0
- Fees
- $1,140
- Days from application to issue
- 10
-
Permit Demolition Application Acceptance - Approved No Review
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.
- Permit
- 09BLD-05602
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Contractor
- Camp Dresser & Mckee
- Days from application to issue
- 5