Central City

1725 ST ANDREW ST is in Central City, zoned HU-RM1 (Older neighborhoods, low-density multi-family housing up to three stories). The city has 6 permits on record here; the most recent, a construction loop permit, was filed in July 2023. 2 are still open. On this block in the past year: 14 requests to 311 and 46 calls to police.

Zoning
HU-RM1
Historic district
None
National Register
Central City Historic District
Council district
B
Ward
10
Lot size
3,206 sq ft
Parcel
41186245

Everything on record here

6 records, newest first · 2 open

  1. Permit Construction Loop Permit Cancelled

    New house

    Permit
    23-18750-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $100,112
    Fees
    $40
    Contractor
    Rolando J Sandoval
    Days from application to issue
    3
    Expires
    Jan 14, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Permit Cancelled

    New house

    Permit
    23-18017-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $100,112
    Fees
    $150
    Contractor
    Rolando J Sandoval
    Days from application to issue
    8
    Expires
    Jan 12, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date

    See this permit on One Stop

  3. Permit HDLC COA Permit Cancelled

    New Construction Planned Unit Development (P.U.D.) on a subdivided lot (originally 1721-35 St. Andrew St. and to be changed to 1725 St. Andrew St. Units A-P). Building 3 is a single-family detached cottage (Unit P) and is part of a Planned Unit Development project with 16 total units. Building 3 is one of four separate buildings on this P.U.D. project site. Detached cottage is 1.5 stories, with a driveway, and contains 2 bedrooms & 2 bathrooms. Construction system consists of heavy timber structural frame, concrete grade beam foundation, Structurally Insulated Panels (SIP), & Steel Stud walls, floors, and roof. Painted fiber cement board exterior wall finish and standing seam metal roof.

    Permit
    21-32502-HDLC
    Type
    HDLC COA
    Work
    HDLC COA
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    Jun 2, 2022

    See this permit on One Stop

  4. Permit HDLC COA Permit Cancelled

    New Construction Planned Unit Development (P.U.D.) on a subdivided lot (originally 1721-35 St. Andrew St. and to be changed to 1725 St. Andrew St. Units A-P). Building 2 consists of seven (7) attached townhouse units (I-O) and is part of a Planned Unit Development project with 16 total units. Building 2 is one of four separate buildings on this P.U.D. project site. Attached Townhomes are 2 stories, with ground floor garage and driveway, and contain 2 bedrooms & 2 bathrooms each. Construction system consists of heavy timber structural frame, concrete grade beam foundation, CMU wall base, Structurally Insulated Panels (SIP), & Steel Stud walls, floors, and roof. Painted fiber cement board exterior wall finish and standing seam metal roof. Attached townhomes are sprinklered and each unit is separated by 1-hour rated demising walls.

    Permit
    21-32496-HDLC
    Type
    HDLC COA
    Work
    HDLC COA
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    May 29, 2022

    See this permit on One Stop

  5. Permit New Construction Permit Issued

    New Construction Planned Unit Development (P.U.D.) on a subdivided lot (originally 1721-35 St. Andrew St. and to be changed to 1725 St. Andrew St. Units A-P). Building 3 is a single-family detached cottage (Unit P) and is part of a Planned Unit Development project with 16 total units. Building 3 is one of four separate buildings on this P.U.D. project site. Detached cottage is 1.5 stories, with a driveway, and contains 2 bedrooms & 2 bathrooms. Construction system consists of heavy timber structural frame, concrete grade beam foundation, Structurally Insulated Panels (SIP), & Steel Stud walls, floors, and roof. Painted fiber cement board exterior wall finish and standing seam metal roof.

    Permit
    21-32502-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $202,489
    Fees
    $1,278
    Contractor
    Concordia LLC, Pace Group LLC, A-1 Developers LLC
    Days from application to issue
    545
    Expires
    Nov 18, 2023
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  6. Permit New Construction Permit Issued

    New Construction Planned Unit Development (P.U.D.) on a subdivided lot (originally 1721-35 St. Andrew St. and to be changed to 1725 St. Andrew St. Units A-P). Building 2 consists of seven (7) attached townhouse units (I-O) and is part of a Planned Unit Development project with 16 total units. Building 2 is one of four separate buildings on this P.U.D. project site. Attached Townhomes are 2 stories, with ground floor garage and driveway, and contain 2 bedrooms & 2 bathrooms each. Construction system consists of heavy timber structural frame, concrete grade beam foundation, CMU wall base, Structurally Insulated Panels (SIP), & Steel Stud walls, floors, and roof. Painted fiber cement board exterior wall finish and standing seam metal roof. Attached townhomes are sprinklered and each unit is separated by 1-hour rated demising walls.

    Permit
    21-32496-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $748,141
    Fees
    $4,554
    Contractor
    Concordia LLC, Pace Group LLC, A-1 Developers LLC
    Days from application to issue
    545
    Expires
    Nov 18, 2023
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop