New Aurora - English Turn

104 Harbour Town Court is in New Aurora - English Turn, zoned S-RS (Newer neighborhoods, single-family homes). The city has 4 permits on record here; the most recent, a permanent generator permit, was filed in July 2022. 1 is still open. On this block in the past year: 3 requests to 311 and 0 calls to police.

Zoning
S-RS
Historic district
None
Council district
C
Ward
15
Lot size
9,819 sq ft
Parcel
41190085

Everything on record here

4 records, newest first · 1 open

  1. Permit Permanent Generator Permit Cancelled

    installing a 26kw generator

    Permit
    22-22712-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $21,947
    Fees
    $103
    Contractor
    John Keefe Keefe
    1. Application submitted

    See this permit on One Stop

  2. Permit Permanent Generator Permit Issued

    Installation of a 26KW whole house generator

    Permit
    22-22575-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $21,947
    Fees
    $103
    Contractor
    Keefe John Ditta
    Days from application to issue
    5
    Expires
    Feb 1, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    installing a 26kw generator

    Permit
    22-20207-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $21,947
    Fees
    $80
    Days from application to issue
    1
    Expires
    Jan 7, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Accessory Structure Permit Issued

    Installing a 26KW whole house generator

    Permit
    22-17903-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $21,947
    Fees
    $230
    Days from application to issue
    21
    Expires
    Jan 6, 2023
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop