City Park

966 Picheloup Place is in City Park, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Parkview historic district under partial HDLC control, where demolition needs HDLC review. The city has 10 permits on record here; the most recent, a mechanical fuel gas permit, was filed in November 2023. On this block in the past year: 21 requests to 311 and 6 calls to police.

Zoning
HU-RD1
Historic district
Parkview (Partial control)
National Register
Parkview Historic District
Council district
A
Ward
5
Lot size
9,962 sq ft
Parcel
41190271

Everything on record here

10 records, newest first

  1. Permit Mechanical Fuel Gas Permit Finaled

    Run a new gas line approximately 40ft from the meter into the basement, then across to the other side. Poke out down low and run underground to the generator. Make final connection to the generator.

    Permit
    23-30902-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $1,745
    Fees
    $50
    Days from application to issue
    1
    Expires
    May 9, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit Electrical Service / Circuit / Feeder Permit Finaled

    We are taking over from a previous contractor and need a an electrical permit.

    Permit
    23-24381-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $15,000
    Fees
    $175
    Contractor
    Robert Falcon, III
    Days from application to issue
    8
    Expires
    Mar 12, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  3. Permit Permanent Generator Permit Finaled

    Install 36Kw Cummins Generator

    Permit
    23-20415-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $34,524
    Fees
    $106
    Contractor
    Jonathan S. Frischhertz
    Days from application to issue
    7
    Expires
    Feb 2, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Moving Equipment Permit Finaled

    Installation Of A Three Stop Savaria Eclipse Elevator.

    Permit
    22-26976-MOVG
    Type
    Moving Equipment
    Work
    Moving Equipment
    Estimated cost (applicant’s figure)
    $0
    Fees
    $95
    Contractor
    H- Worth Elevator Co
    Days from application to issue
    0
    Expires
    Mar 7, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Accessory Structure Occupancy

    INSTALL (1) 36KW PERMANENT STANDBY GENERATOR AS PER PLANS.

    Permit
    22-18517-ACCS
    Type
    Accessory Structure
    Work
    Accessory Structure
    Estimated cost (applicant’s figure)
    $34,524
    Fees
    $295
    Contractor
    Jonathan S. Frischhertz
    Days from application to issue
    401
    Expires
    Jan 26, 2024
    1. Application submitted
    2. Zoning review
    3. Application review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  6. Permit Mechanical HVAC Permit Finaled

    Installation of (1) 2.5 ton and (1) 3 ton units

    Permit
    22-13172-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $69,211
    Fees
    $100
    Contractor
    Burkhardt III P John
    Days from application to issue
    0
    Expires
    Nov 3, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Mechanical Fuel Gas Permit Finaled

    2 tankless water heaters/ 2 heating units/ 2 dryers/ 2 stoves/1 fireplace

    Permit
    22-08826-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $43,850
    Fees
    $149
    Contractor
    Garrison Builders, LLC
    Days from application to issue
    56
    Expires
    Nov 23, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit Renovation (Structural) Occupancy

    Renovation of, and addition to, an existing wood-framed two-family residence as per plans. **NEED FINAL FEMA Elevation Certificate for FINAL INSPECTION showing flood openings** Extend permit to December 7, 2023.

    Permit
    21-23483-RNVS
    Type
    Renovation (Structural)
    Work
    Renovation (Structural)
    Estimated cost (applicant’s figure)
    $858,278
    Fees
    $5,409
    Contractor
    Fritscher Construction Co, Garrison Builders, LLC
    Days from application to issue
    56
    Expires
    Apr 7, 2022
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  9. Permit Construction Loop Permit Finaled

    Temporary construction Loop

    Permit
    21-12280-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $400
    Fees
    $40
    Contractor
    Francis Ronald Jouandot
    Days from application to issue
    5
    Expires
    Nov 4, 2021
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  10. Permit Interior Demolition Permit Cancelled

    Complete interior demolition. Full renovation building permit to follow after demolition is complete

    Permit
    21-08940-DEMI
    Type
    Interior Demolition
    Work
    Interior Demolition
    Estimated cost (applicant’s figure)
    $19,500
    Fees
    $160
    Contractor
    Bertel Construction LLC
    Days from application to issue
    28
    Expires
    Oct 27, 2021
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Permit approved
    5. Issue date
    6. First inspection

    See this permit on One Stop