6017 Wickfield Drive is in St. Anthony, zoned S-RS (Newer neighborhoods, single-family homes). The city has 7 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in December 2010. 7 are still open. A demolition permit was filed in December 2009. There were 2 past code enforcement cases, the latest in January 2026, all closed. On this block in the past year: 5 requests to 311 and 16 calls to police.
- Zoning
- S-RS
- Historic district
- None
- Council district
- D
- Ward
- 7
- Lot size
- 9,543 sq ft
- Parcel
- 41192558
Everything on record here
9 records, newest first · 7 open
-
Code enforcement Case 26-00286-MPM Closed
The property was inspected on 01/09/2026 with a finding of "No Violation". The file was subsequently closed.
- Inspection: Inspection No Violation
The city links this case to permit 10ELC-12984.
-
Permit Electrical Service / Circuit / Feeder Permit Issuance - Active
NEW CONSTRUCTION- 10BLD-05530
- Permit
- 10ELC-12984
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $148
- Contractor
- Coastal Electric, Inc
- Days from application to issue
- 0
-
Permit General Mechanical Inspection - Completed
INSTALL ELEC WAF AND A\C. (#10BLD-05532) ROBERT GOODWIN (#7019)
- Permit
- 10MCH-10049
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $70
- Contractor
- Rob's A/C & Heating
- Days from application to issue
- 0
-
Permit Construction Loop Permit Issuance - Active
TEMP POLE- 10BLD-05530
- Permit
- 10ELC-10926
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Coastal Electric, Inc
- Days from application to issue
- 0
-
Permit New Construction Inspection - Completed
NEW CONSTRUCTION OF A 1-STORY SINGLE FAMILY DWELLING AS PER PLANS.
- Permit
- 10BLD-05532
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $156,000
- Fees
- $996
- Days from application to issue
- 19
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLISH SINGLE FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.
- Permit
- 09BLD-07957
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Contractor
- Camp Dresser & Mckee
- Days from application to issue
- 5
-
Permit Demolition Certificate of Occupancy - Issued No Meter
PERMIT ISSUED TO DEMOLISH SLAB ONLY.
- Permit
- 09BLD-07394
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $5,000
- Fees
- $100
- Contractor
- Camp Dresser & Mckee,
- Days from application to issue
- 5
-
Code enforcement Case ENVHADJ-2007338EH Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 10ELC-12984.
-
Permit Demolition Inspection - Completed
Demolition of hurricane damaged single residential unit. Contractor to remove and dispose of all debris within 72 hours and to have a final inspection of the site. A licensed plumber must secure a seperate permit from the Sewage and Water Board to cap off sewer lines and remove water meters prior to demolition.
- Permit
- 07BLD-07463
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $50
- Days from application to issue
- 5