Central City
2706 Saint Andrew Street is in Central City, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 9 permits on record here; the most recent, a plumbing permit, was filed in May 2026. 7 are still open. A demolition permit was filed in April 2008. There was 1 past code enforcement case, the latest in April 2009, all closed. On this block in the past year: 3 requests to 311 and 4 calls to police.
- Zoning
- HU-RD2
- Historic district
- None
- National Register
- Central City Historic District
- Council district
- B
- Ward
- 10
- Lot size
- 2,123 sq ft
- Parcel
- 41206468
Everything on record here
10 records, newest first · 7 open
-
Permit Plumbing Permit Permit Issued
WATER METER RESET
- Permit
- 26-14181-PLMB
- Type
- Plumbing Permit
- Work
- Plumbing Permit
- Estimated cost (applicant’s figure)
- $0
- Fees
- $100
- Contractor
- Jamal Donnell Every
- Days from application to issue
- 0
- Expires
- Nov 11, 2026
-
Permit Electrical Vacancy Other
Vacancy and repairs Last service date was 03/17/2016
- Permit
- 24-37329-EVAC
- Type
- Electrical Vacancy
- Work
- Electrical Vacancy
- Estimated cost (applicant’s figure)
- $950
- Fees
- $40
- Contractor
- Eugene J Lawrence Jr.
- Days from application to issue
- 35
- Expires
- Jul 16, 2025
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Renovation (Non-Structural) Other
Vacancy Inspection, NO WORK Required Utilities OFF over 2 years
- Permit
- 24-37313-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $1,150
- Fees
- $130
- Contractor
- E-1 Electric, LLC
- Days from application to issue
- 29
- Expires
- Jul 10, 2025
- Application submitted
- Zoning review
- Application review
- Plan review
- Permit approved
- Issue date
-
Permit Electrical Vacancy Permit Issued
VACANCY
- Permit
- 13-13131-EVAC
- Type
- Electrical Vacancy
- Work
- Electrical Vacancy
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Elbred Malone
- Days from application to issue
- 0
- Expires
- Oct 28, 2013
-
Permit Electrical Service / Circuit / Feeder Permit Issuance - Active
NEW CONSTRUCTION- 09BLD-04265
- Permit
- 10ELC-05250
- Type
- Electrical Service / Circuit / Feeder
- Work
- Service-Circuits-Feeders
- Estimated cost (applicant’s figure)
- $0
- Fees
- $127
- Contractor
- First Contact Electric
- Days from application to issue
- 0
-
Permit Construction Loop Application Acceptance - Approved
TEMP POLE- 09BLD-04265
- Permit
- 09ELC-14086
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $30
- Contractor
- First Contact Electric
- Days from application to issue
- 10
-
Permit New Construction Inspection - Completed
NEW CONSTRUCTION OF A 2-STRY, 1500 SF SINGLE FAMILY RESIDENCE AS PER PLANS. FY ave=7'-0" RY ave 14'-6"
- Permit
- 09BLD-04265
- Type
- New Construction
- Work
- New
- Estimated cost (applicant’s figure)
- $127,500
- Fees
- $818
- Contractor
- Myers & Sons Enterprises Inc
- Days from application to issue
- 9
-
Code enforcement Case ENVHADJ-2003193HB Closed
A hearing was held on 04/10/2009 with a result of "Found Guilty". The case was subsequently closed.
- Inspection: Inspection Complete
- Hearing: Initial Hearing Found Guilty
The city links this case to permit 26-14181-PLMB.
-
Permit Demolition Certificate of Occupancy - Issued No Meter
DEMOLISH DOUBLE FAMILY HOUSE TO GRADE. HOUSE IS IN IMMINENT DANGER OF COLLAPSE (PER JOHNNY ODOM).CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS.
- Permit
- 08BLD-02348
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $3,000
- Fees
- $90
- Days from application to issue
- 5
-
Permit Demolition Inspection - Completed No Requirements
DEMOLISH TWO FAMILY HOUSE TO GRADE. CONTRACTOR SHALL REMOVE AND DISPOSE OF ALL DEBRIS WITHIN 72 HOURS OF COMPLETION. PROOF OF DISPOSAL REQUIRED AT TIME OF FINAL INSPECTION. SEPARATE PERMIT REQUIRED FROM SEWERAGE AND WATER BOARD TO CAP SEWER LINES AND REMOVE WATER METERS. DOUBLE 2706-08 ST ANDREWS
- Permit
- 08BLD-01218
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $125
- Contractor
- Drc Emergency Servces,Llc, Drc Emergency Servces,Llc
- Days from application to issue
- 6