1033 Moss Street is in City Park, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Parkview historic district under partial HDLC control, where demolition needs HDLC review. The city has 11 permits on record here; the most recent, a permanent generator permit, was filed in December 2019. 3 are still open. On this block in the past year: 11 requests to 311 and 4 calls to police.

Zoning
HU-RD1
Historic district
Parkview (Partial control)
National Register
Esplanade Ridge Historic District
Council district
A
Ward
5
Lot size
9,062 sq ft
Parcel
41209172

Everything on record here

11 records, newest first · 3 open

  1. Permit Permanent Generator In Review

    GENERATOR

    Permit
    19-70566-EGEN
    Type
    Permanent Generator
    Work
    Permanent Generator
    Estimated cost (applicant’s figure)
    $0
    Fees
    $618
    Contractor
    Brian David Melan
    1. Application submitted
    2. Application review

    See this permit on One Stop

  2. Permit Mechanical Fuel Gas Permit Finaled

    Install 10' of 3/4" gas pipe to pool heater

    Permit
    19-70620-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $240
    Contractor
    Casey J Sutton
    Days from application to issue
    0
    Expires
    Jun 30, 2020
    1. Issue date
    2. First inspection
    3. Application submitted
    4. Application review
    5. Permit approved

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    Run gas lines to generator

    Permit
    19-70510-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $0
    Fees
    $50
    Contractor
    Wesley Gray Williams
    Days from application to issue
    110
    Expires
    Oct 15, 2020
    1. First inspection
    2. Application submitted
    3. Application review
    4. Permit approved
    5. Issue date

    See this permit on One Stop

  4. Permit Renovation (Non-Structural) Other

    Permit for installation of generator. To be located at or above required flood elevation.

    Permit
    19-70177-RNVN
    Type
    Renovation (Non-Structural)
    Work
    Renovation (Non-Structural)
    Estimated cost (applicant’s figure)
    $15,493
    Fees
    $200
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved

    See this permit on One Stop

  5. Permit Swimming Pool Permit Issued

    Install in ground gunite pool and spa 12 x 36

    Permit
    19-27889-POOL
    Type
    Swimming Pool
    Work
    Swimming Pool
    Estimated cost (applicant’s figure)
    $69,210
    Fees
    $480
    Days from application to issue
    8
    Expires
    Mar 11, 2020
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date

    See this permit on One Stop

  6. Permit Electrical Service / Circuit / Feeder Permit Finaled

    18-37430-newc

    Permit
    19-18287-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $7,000
    Fees
    $169
    Contractor
    Brian David Melan
    Days from application to issue
    0
    Expires
    Dec 6, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit Mechanical HVAC Permit Issued

    Install one 1.5 electric system with ductwork. Install one 2 ton and one 3 ton Heat Pump system with ductwork.

    Permit
    19-14817-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $35,000
    Fees
    $75
    Contractor
    Brandon Construction
    Days from application to issue
    5
    Expires
    Nov 14, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit Mechanical Fuel Gas Permit Finaled

    Gas System for: 2-Water Heater, 3-Furnace, 2-BBQ, Cooktop, Fireplace, Dryer, Pool heater stub-out, Lantern, Generator stub-out

    Permit
    19-04812-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $6,500
    Fees
    $137
    Days from application to issue
    0
    Expires
    Aug 13, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  9. Permit Construction Loop Permit Finaled

    #18-37430-NEWC

    Permit
    19-02112-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $8,000
    Fees
    $40
    Contractor
    Brian David Melan
    Days from application to issue
    0
    Expires
    Jul 22, 2019
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  10. Permit Change of Address Permit Issued

    18-37430-NEWC 1035 Moss St Keep 1033 Moss St Retire

    Permit
    18-37485-ECOA
    Type
    Change of Address
    Work
    Change of Address
    Estimated cost (applicant’s figure)
    $0
    Fees
    $0
    Days from application to issue
    0
    Expires
    May 12, 2019
    1. Application submitted
    2. Permit approved
    3. Issue date

    See this permit on One Stop

    Placed here by an address range from “1033-1035 Moss St”.

  11. Permit New Construction Permit Issued

    New construction two-story 3116 sq ft single family residence as per plans. Pool to be constructed under seperate permit, not included in this permit.

    Permit
    18-37430-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $1,204,290
    Fees
    $7,290
    Contractor
    Kenneth Gowland, James Heaslip, Brandon Construction
    Days from application to issue
    59
    Expires
    Jul 10, 2019
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop