Lakewood
110 Sharon Drive is in Lakewood, zoned S-LRS3 (Lake area single-family homes). The city has 8 permits on record here; the most recent, a solar permit, was filed in May 2024. 3 are still open. A demolition permit was filed in April 2006. There were 3 past code enforcement cases, the latest in May 2011, all closed. On this block in the past year: 2 requests to 311 and 1 call to police.
- Zoning
- S-LRS3
- Historic district
- None
- Council district
- A
- Ward
- 17
- Lot size
- 4,937 sq ft
- Parcel
- 41213187
Everything on record here
11 records, newest first · 3 open
-
Permit Solar Permit Finaled
Solar-check meter and wiring
- Permit
- 24-13929-SOLR
- Type
- Solar
- Work
- Solar
- Estimated cost (applicant’s figure)
- $12,000
- Fees
- $61
- Contractor
- Glynn Raye Woodall, Jr
- Days from application to issue
- 15
- Expires
- Nov 23, 2024
-
Permit Renovation (Non-Structural) Occupancy
Install 6.03 kW solar panel system on existing building-no structural changes
- Permit
- 24-13086-RNVN
- Type
- Renovation (Non-Structural)
- Work
- Renovation (Non-Structural)
- Estimated cost (applicant’s figure)
- $17,000
- Fees
- $205
- Contractor
- PosiGen Developer LLC
- Days from application to issue
- 1
- Expires
- Nov 3, 2024
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
- First inspection
-
Permit General Mechanical Permit Finaled
install gas tankless water heater, gas line and gas lighrt. Alton Ostarly Jr (#19026) 12-26081-NEWC
- Permit
- 13-35543-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $60
- Contractor
- Alton J Ostarly Jr
- Days from application to issue
- 0
- Expires
- Feb 23, 2014
-
Permit Electrical Service / Circuit / Feeder Permit Issued
NEW CONSTRUCTION- 12-26081
- Permit
- 13-08004-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $0
- Fees
- $172
- Contractor
- Donald Wiltz Fabacher
- Days from application to issue
- 0
- Expires
- Sep 14, 2013
-
Permit General Mechanical Permit Finaled
install condenser unit. stephen corcoran (#2609) 12-26081-NEWC /NEED PERMITS FOR WATER & HEAT
- Permit
- 13-07004-MECH
- Type
- General Mechanical
- Work
- General Mechanical
- Estimated cost (applicant’s figure)
- $0
- Fees
- $45
- Contractor
- Stephen Corcoran
- Days from application to issue
- 6
- Expires
- Sep 12, 2013
-
Permit Construction Loop Permit Issued
TEMP POLE- 12-26081
- Permit
- 12-33955-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $0
- Fees
- $40
- Contractor
- Donald Wiltz Fabacher
- Days from application to issue
- 0
- Expires
- Jun 19, 2013
-
Permit New Construction Permit Finaled
Construct a 1680 sq ft 1 story single-family dwelling as per plans.
- Permit
- 12-26081-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $168,000
- Fees
- $1,113
- Contractor
- GWEN LORIA
- Days from application to issue
- 20
- Expires
- Apr 22, 2013
-
Code enforcement Case CEHB-11-3358 Closed
The case was filed on 05/23/2011 but has since been closed without further action.
- Inspection: Inspection Abated
The city links this case to permit 24-13929-SOLR.
-
Code enforcement Case HCEVU-11-02452 Closed
The property was inspected on 03/29/2011 with a finding of "Violation Unoccupied". The file was subsequently closed.
- Inspection: Inspection Violation Unoccupied
The city links this case to permit 24-13929-SOLR.
-
Code enforcement Case HCEC-11-00964 Closed
The case was filed on 03/22/2011 but has since been closed without further action.
The city links this case to permit 24-13929-SOLR.
-
Permit Demolition Inspection - Completed No Requirements
DEMOLITION- PLANS TO REBUILD. CONTRACTOR MUST REMOVE ALL DEBRIS WITHIN 72 HOURS AND HAVE A FINAL INSPECTION OF THE SITE. PROOF OF PROPER DISPOSAL OF THE DEBRIS REQUIRED AT TIME OF FINAL INSPECTION. 53.81% LAKEVIEW DISTRICT.
- Permit
- 06BLD-03159
- Type
- Demolition
- Work
- Demolition
- Estimated cost (applicant’s figure)
- $3,000
- Fees
- $90
- Days from application to issue
- 5