Whitney
1117 Patterson Street is in Whitney, zoned HU-MU (Older neighborhoods, walkable mix of shops with homes above). The city has 6 permits on record here; the most recent, a mechanical fuel gas permit, was filed in July 2023. On this block in the past year: 5 requests to 311 and 1 call to police.
- Zoning
- HU-MU
- Historic district
- None
- Council district
- C
- Ward
- 15
- Lot size
- 2,445 sq ft
- Parcel
- 51001952
Everything on record here
6 records, newest first
-
Permit Mechanical Fuel Gas Permit Finaled
6 month gas test
- Permit
- 23-18184-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $300
- Fees
- $30
- Contractor
- Jack O Wilson, Jr
- Days from application to issue
- 6
- Expires
- Jan 12, 2024
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical Fuel Gas Permit Finaled
Gas-New Construction
- Permit
- 21-20173-FGAS
- Type
- Mechanical Fuel Gas
- Work
- Mechanical Fuel Gas
- Estimated cost (applicant’s figure)
- $3,250
- Fees
- $40
- Days from application to issue
- 2
- Expires
- Jan 15, 2022
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Mechanical HVAC Permit Finaled
Install 4 ton 14seer system with 15kw electric air handler.
- Permit
- 20-44194-HVAC
- Type
- Mechanical HVAC
- Work
- Mechanical HVAC
- Estimated cost (applicant’s figure)
- $10,000
- Fees
- $88
- Contractor
- Mike Bertel
- Days from application to issue
- 1
- Expires
- Apr 20, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit New Construction Occupancy
New Construction of Single Family Home
- Permit
- 20-03376-NEWC
- Type
- New Construction
- Work
- New Construction
- Estimated cost (applicant’s figure)
- $225,431
- Fees
- $1,416
- Days from application to issue
- 363
- Expires
- Feb 11, 2022
- First inspection
- Application submitted
- Application review
- Zoning review
- Plan review
- Permit approved
- Issue date
-
Permit Electrical Service / Circuit / Feeder Permit Finaled
Complete wire and low voltage. NEED BUILDING PERMIT
- Permit
- 20-35617-SERV
- Type
- Electrical Service / Circuit / Feeder
- Work
- Electrical Service / Circuit / Feeder
- Estimated cost (applicant’s figure)
- $10,649
- Fees
- $129
- Contractor
- Jaime Andres Ordonez
- Days from application to issue
- 28
- Expires
- Feb 21, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection
-
Permit Construction Loop Permit Finaled
Temp. Pole NEED BUILDING PERMIT
- Permit
- 20-35615-LOOP
- Type
- Construction Loop
- Work
- Construction Loop
- Estimated cost (applicant’s figure)
- $10,649
- Fees
- $40
- Contractor
- Jaime Andres Ordonez
- Days from application to issue
- 32
- Expires
- Feb 25, 2021
- Application submitted
- Application review
- Permit approved
- Issue date
- First inspection