Bywater

1435 Lesseps Street is in Bywater, zoned HU-RD2 (Older neighborhoods, two-family homes mixed with single-family homes). The city has 7 permits on record here; the most recent, an electrical service / circuit / feeder permit, was filed in December 2023. On this block in the past year: 8 requests to 311 and 13 calls to police.

Zoning
HU-RD2
Historic district
None
National Register
Bywater Historic District Extension
Council district
D
Ward
9
Lot size
3,584 sq ft
Parcel
51001988

Everything on record here

7 records, newest first

  1. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Electrical permit being extended to the previous permit # 23-00853-Serv. 200 AMP SERV & 26 CIRCUITS.

    Permit
    23-34046-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $11,400
    Fees
    $172
    Contractor
    Russell Jamal Frank
    Days from application to issue
    23
    Expires
    Jul 5, 2024
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  2. Permit New Construction Permit Cancelled

    22-21706-NEWC Need to renewal expired permit

    Permit
    23-34044-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $0
    Fees
    $120
    Contractor
    Eagle One LLC
    1. Application submitted

    See this permit on One Stop

  3. Permit Mechanical HVAC Permit Finaled

    Filing Fees for installing 3.5 Ton HVAC gas system. 10-drop flexible duct system. One minisplit system 18,000.

    Permit
    23-01907-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $15,000
    Fees
    $125
    Days from application to issue
    6
    Expires
    Jul 26, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Mechanical Fuel Gas Permit Finaled

    INSTALL NEW GAS LINE (5) OUTLETS AND TANKLESS WATER HEATER

    Permit
    23-01683-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $4,500
    Fees
    $40
    Days from application to issue
    6
    Expires
    Jul 24, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Electrical Service / Circuit / Feeder Permit Cancelled

    NEWC-Wire( Romex ) with a 200 amp Serv& 26 circuits.

    Permit
    23-00853-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $11,400
    Fees
    $178
    Contractor
    Russell Jamal Frank
    Days from application to issue
    14
    Expires
    Jul 24, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Construction Loop Permit Finaled

    Install 100-amp Temp pole. Edgar Young 813-0256

    Permit
    22-26527-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $650
    Fees
    $40
    Contractor
    Edgar Young Jr.
    Days from application to issue
    1
    Expires
    Mar 1, 2023
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  7. Permit New Construction Occupancy

    building a Single Family Home 2300 Sqft Permit Extended (3) 180 day periods to July 3, 2024.

    Permit
    22-21706-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $222,900
    Fees
    $1,593
    Days from application to issue
    38
    Expires
    Feb 26, 2023
    1. Application submitted
    2. Plan review
    3. Application review
    4. Zoning review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop