Milan

2229 Peniston Street is in Milan, zoned HU-RD1 (Older neighborhoods, two-family homes on smaller lots). It is in the Uptown historic district under partial HDLC control, where demolition needs HDLC review. The city has 7 permits on record here; the most recent, a street cut permit, was filed in March 2022. There were 2 past code enforcement cases, the latest in January 2023, all closed. On this block in the past year: 8 requests to 311 and 10 calls to police.

Zoning
HU-RD1
Historic district
Uptown (Partial control)
National Register
Uptown New Orleans Historic District
Council district
B
Ward
12
Lot size
3,488 sq ft
Parcel
51002576

Everything on record here

9 records, newest first

  1. Code enforcement Case 23-00185-MPM Closed

    The property was inspected on 01/19/2023 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 22-07903-RSTC.

  2. Permit Street Cut Inspection Phase

    install one 6"shc; install one 5/8" meter

    Permit
    22-07903-RSTC
    Type
    Street Cut
    Work
    Street Cut
    Estimated cost (applicant’s figure)
    $0
    Fees
    $535
    Contractor
    JLJ Electrical And A/C
    Days from application to issue
    19
    Expires
    Oct 4, 2022

    See this permit on One Stop

  3. Permit Mechanical Fuel Gas Permit Finaled

    install new gas line to supply stove,dryer,heater,and water heater and will install 30 gallon water heater

    Permit
    22-06321-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $2,560
    Fees
    $35
    Days from application to issue
    9
    Expires
    Sep 11, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  4. Permit Mechanical HVAC Permit Finaled

    Install one 5 ton electric system and ductwork

    Permit
    21-33662-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $7,995
    Fees
    $71
    Days from application to issue
    6
    Expires
    Jun 9, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  5. Permit Electrical Service / Circuit / Feeder Permit Finaled

    Wiring for new construction with a new service

    Permit
    21-32345-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $5,000
    Fees
    $181
    Contractor
    Dennis Leon deBoisblanc Sr.
    Days from application to issue
    12
    Expires
    Jun 6, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  6. Permit Dumpster/Construction Zone Other

    Construction dumpster

    Permit
    21-28402-RCZD
    Type
    Dumpster/Construction Zone
    Work
    Dumpster/Construction Zone
    Estimated cost (applicant’s figure)
    $0
    Fees
    $490
    Contractor
    Asper Construction & Development Group
    Days from application to issue
    0
    Expires
    Apr 11, 2022

    See this permit on One Stop

  7. Permit Construction Loop Permit Finaled

    Temp pole installation

    Permit
    21-26264-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $200
    Fees
    $40
    Contractor
    Dennis Leon deBoisblanc Sr.
    Days from application to issue
    1
    Expires
    Mar 23, 2022
    1. Application submitted
    2. Application review
    3. Permit approved
    4. Issue date
    5. First inspection

    See this permit on One Stop

  8. Permit New Construction Occupancy

    Construction of a new single-family residence

    Permit
    21-24268-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $314,942
    Fees
    $1,950
    Contractor
    Asper Construction and Development Group LLC
    Days from application to issue
    35
    Expires
    Mar 22, 2022
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop

  9. Code enforcement Case 21-00200-MPM Closed

    The property was inspected on 01/19/2023 with a finding of "No Violation". The file was subsequently closed.

    1. Inspection: Inspection No Violation

    The city links this case to permit 22-07903-RSTC.