Filmore

1853 Pratt Drive is in Filmore, zoned S-RS (Newer neighborhoods, single-family homes). The city has 8 permits on record here; the most recent, a mechanical fuel gas permit, was filed in September 2026. 7 are still open. On this block in the past year: 4 requests to 311 and 3 calls to police.

Zoning
S-RS
Historic district
None
Council district
D
Ward
7
Lot size
3,566 sq ft
Parcel
51003499

Everything on record here

8 records, newest first · 7 open

  1. Permit Mechanical Fuel Gas Permit Issued

    New gas line. New water heater,stove,dryer,and A/C

    Permit
    26-28472-FGAS
    Type
    Mechanical Fuel Gas
    Work
    Mechanical Fuel Gas
    Estimated cost (applicant’s figure)
    $1,750
    Fees
    $240
    Contractor
    William Leroy Hoffman, Jr
    Days from application to issue
    8
    Expires
    Apr 6, 2027
    1. Gas Line and Outlets Paid
    2. Mechanical Permit Violation Unpaid
    3. Water Heaters Paid
    4. Gas Line
    5. Water Heater
    6. Application Submitted Complete
    7. Application Review Complete
    8. Permit Approved Complete
    9. Mechanical Permit Review Complete
    10. Mechanical Permit Review Pending
    11. Application submitted
    12. Application review
    13. Permit approved
    14. Rough Mech Gas Res Passed
    15. Permit Issued Complete
    16. Issue date

    See this permit on One Stop

  2. Permit Mechanical HVAC Permit Issued

    To install two 2 1/2-ton 454B electric systems. This includes air handlers, condensers, ductwork, and copper grills. Thermostats will be provided at the end of the job. Labor and materials are included.

    Permit
    26-28231-HVAC
    Type
    Mechanical HVAC
    Work
    Mechanical HVAC
    Estimated cost (applicant’s figure)
    $263,085
    Fees
    $100
    Contractor
    Larry Terrance Bentley
    Days from application to issue
    1
    Expires
    Mar 25, 2027
    1. Air Conditioning Paid
    2. Mechanical Paid
    3. Warm Air Furnaces Paid
    4. Duct Leakage
    5. Warm Air Furnace
    6. Whole House Infiltration
    7. Air Conditioning
    8. Application Submitted Complete
    9. Application Review Complete
    10. Permit Approved Complete
    11. Mechanical Permit Review Complete
    12. Application submitted
    13. Application review
    14. Permit approved
    15. Permit Issued Complete
    16. Issue date
    17. Rough Mech HVAC Res Passed
    18. First inspection

    See this permit on One Stop

  3. Permit Plumbing Permit Permit Issued

    New construction, new PEX water lines, new PVC drains and vents, new fixtures

    Permit
    26-25768-PLMB
    Type
    Plumbing Permit
    Work
    Plumbing Permit
    Estimated cost (applicant’s figure)
    $0
    Fees
    $150
    Contractor
    Jack O Wilson, Jr
    Days from application to issue
    0
    Expires
    Mar 2, 2027
    1. SWB Filing Fee Paid
    2. Plumbing Underground
    3. Plumbing Tie In
    4. Plumbing Final
    5. Application Submitted Complete
    6. Application Review (SWB) Complete
    7. Permit Approved Complete
    8. Permit Issued Complete
    9. SWBNO Plumbing Intake Approved
    10. SWBNO Plumbing Approval Approved
    11. Plumbing Rough In/ Top Out Passed

    See this permit on One Stop

  4. Permit Electrical Service / Circuit / Feeder Permit Issued

    Wire a single family new construction

    Permit
    26-23625-SERV
    Type
    Electrical Service / Circuit / Feeder
    Work
    Electrical Service / Circuit / Feeder
    Estimated cost (applicant’s figure)
    $13,000
    Fees
    $133
    Contractor
    Igor Fernandes Miranda
    Days from application to issue
    2
    Expires
    Feb 13, 2027
    1. Electrical Paid
    2. Final Electric
    3. UG Electrical
    4. Application Submitted Complete
    5. Application submitted
    6. Application Review Complete
    7. Permit Approved Complete
    8. Permit Issued Complete
    9. Electrical Complete
    10. Application review
    11. Permit approved
    12. Issue date
    13. Rough Electrical Passed
    14. First inspection

    See this permit on One Stop

  5. Permit Construction Loop Other

    Temporary power for a residential new construction site

    Permit
    26-23624-LOOP
    Type
    Construction Loop
    Work
    Construction Loop
    Estimated cost (applicant’s figure)
    $13,000
    Fees
    $40
    Contractor
    Igor Fernandes Miranda
    Days from application to issue
    2
    Expires
    Feb 13, 2027
    1. Electrical Paid
    2. Temporary Pole
    3. Application Submitted Complete
    4. Application submitted
    5. Application Review Complete
    6. Permit Approved Complete
    7. Permit Issued Complete
    8. Electrical Complete
    9. Application review
    10. Permit approved
    11. Issue date
    12. Construction Pole (Loop) Passed
    13. First inspection
    14. Certificate of Completion Complete
    15. Meter Release Complete

    See this permit on One Stop

  6. Permit Driveway/ Curb Cut and Restoration Application Accepted

    Driveway/ Curb cut

    Permit
    26-18190-RDRV
    Type
    Driveway/ Curb Cut and Restoration
    Work
    Driveway/ Curb Cut and Restoration
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Contractor
    Cassio Santos

    See this permit on One Stop

  7. Permit Sidewalk Repair Permit Issued

    Sidewalk/ Curb

    Permit
    26-16665-RSWR
    Type
    Sidewalk Repair
    Work
    Sidewalk Repair
    Estimated cost (applicant’s figure)
    $0
    Fees
    $100
    Contractor
    Cassio Santos
    Days from application to issue
    69
    Expires
    Feb 11, 2027

    See this permit on One Stop

  8. Permit New Construction Permit Issued

    New construction of 2,059 sq ft, 2-story, single family home with driveway. To be built as per plans.

    Permit
    26-08917-NEWC
    Type
    New Construction
    Work
    New Construction
    Estimated cost (applicant’s figure)
    $263,085
    Fees
    $1,644
    Contractor
    Strong Shield Siding LLC
    Days from application to issue
    153
    Expires
    Feb 24, 2027
    1. Application submitted
    2. Application review
    3. Zoning review
    4. Plan review
    5. Permit approved
    6. Issue date
    7. First inspection

    See this permit on One Stop